List of Infrastructure Projects – State Wise
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
- Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
- Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
- Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
No. of Projects in this Report: | 9243 | Total Project Cost(in Rs Crore): | 6,813,036.84 |
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
1621 | Coal Based Power (Hosahalli) Project* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Karnataka | Shantha Projects Limited | Under Construction | 52.00 | Not Available | 25-10-2019 |
1622 | Wind Power (Jaora and Piploda) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Madhya Pradesh | Shankheshwer Wind Power Construction Private Limited | Under Construction | 220.50 | 14-Aug-2013 | 28-03-2016 |
1623 | Wind Power (Daloda-10.5 MW) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Madhya Pradesh | Shankheshwar Wind Power Developers Private Limited | Under Construction | 73.50 | 14-Aug-2013 | 22-07-2016 |
1624 | Setting up of 15 MW biomass based power unit in Chhindwara district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Madhya Pradesh | Shalivahana Green Energy Limited | Completed | 75.00 | 30-Jun-2010 | 28-11-2016 |
1625 | Setting up of 10 MW biomass based power unit at Bharouli in Umaria district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Madhya Pradesh | Shalivahana (Biomass) Power Projects Limited | Completed | 50.00 | 30-Apr-2010 | 09-11-2016 |
1626 | Implementation of 11 MLD sewerage scheme at Navelim * | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Sewage collection, treatment and disposal system | Goa | Sewerage & Infrastructural Development Corporation of Goa Limited | Under Construction | 293.00 | 30-Oct-2013 | 25-11-2019 |
1627 | Implementation of 7.5 MLD sewerage scheme at Navelim (Phase I) * | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Sewage collection, treatment and disposal system | Goa | Sewerage & Infrastructural Development Corporation of Goa Limited | Under Construction | 95.00 | 30-Nov-2013 | 25-11-2019 |
1628 | Implementation of 15.5 MLD sewerage scheme in Margao town | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Sewage collection, treatment and disposal system | Goa | Sewerage & Infrastructural Development Corporation of Goa Limited | Completed | 208.00 | 30-May-2009 | 05-12-2017 |
1629 | Implementation of 18.9 MW wind based power units at Valsang & Umrani | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Maharashtra | Serum Institute of India Limited | Completed | 96.39 | 28-Feb-2012 | 01-05-2017 |
1630 | Special Economic Zone (Hadapsar) | Government Infrastructure Projects (Traditional Procurement) | Social and Commercial Infrastructure | Common infrastructure for industrial parks, SEZ | Maharashtra | Serum Institute of India Limited | Completed | 1,200.00 | 28-Feb-2006 | 03-10-2016 |
1631 | Setting up of 40 MW solar power unit at Katol MIDC Area in Nagpur district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Maharashtra | Sepset Constructions Limited | Completed | 280.00 | 10-Mar-2016 | 20-11-2019 |
1632 | Wind Power (Rojwas) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Madhya Pradesh | Sembcorp Green Infra Limited | Completed | 300.00 | 29-Oct-2015 | 23-06-2016 |
1633 | Setting up of 1320 MW coal based power unit at Krishnapatnam, Muthukur mandal in Nellore | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Andhra Pradesh | Sembcorp Gayatri Power Limited | Completed | 9,046.90 | 28-Nov-2013 | 05-11-2019 |
1634 | Setting up a 22 MW captive coal based power unit at Nawanshahr | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Punjab | SEL Manufacturing Company Limited | Completed | 95.00 | 31-May-2009 | 25-04-2017 |
1635 | Setting up of 30 MW Solar Power unit at Kalyan Singh Ki Sid in Jodhpur district under JNNSM Phase II | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Rajasthan | SEI Suryalabh Private Limited | Completed | 210.00 | 25-Jan-2012 | 31-10-2016 |
1636 | Setting up of 10 MW solar power unit at Gowriganipalli & Manepalli in Anantapur district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | SEI Sriram Power Private Limited | Completed | 85.07 | 30-Sep-2012 | 05-12-2016 |
1637 | Setting up of 20 MW solar based power unit at Ugarsh | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Rajasthan | SEI Solar Energy Private Limited | Completed | 200.00 | 08-Oct-2012 | 25-05-2017 |
1638 | Setting up of 5 MW solar photovoltaic power unit at Rewara | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Rajasthan | SEI Solar Energy Private Limited | Completed | 210.00 | 30-Aug-2011 | 25-05-2017 |
1639 | Setting up of 50 MW solar based power unit in Virudhunagar district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Tamil Nadu | SEI Phoebus Private Limited | Completed | 350.00 | 31-Jan-2015 | 28-11-2016 |
1640 | Setting up of 50 MW solar photovoltaic based power unit at Tiruchuli in Virudhunagar district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Tamil Nadu | SEI Kathiravan Power Private Limited | Completed | 336.00 | 15-Nov-2015 | 09-11-2016 |
1641 | Setting up of 10 MW Solar Power unit at Mangoon in Perambalur district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Tamil Nadu | SEI Adityashakti Private Limited | Completed | 70.00 | 31-Dec-2014 | 31-10-2016 |
1642 | Solar Power (Veltoor) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Telangana | SE Solar Limited | Completed | 1,000.00 | 13-Jan-2016 | 21-11-2019 |
1643 | Implementation of 41 MLD sewerage scheme in Satna* | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Sewage collection, treatment and disposal system | Madhya Pradesh | Satna Municipal Corporation | Pre-construction Stage | 206.00 | 31-Dec-2016 | 04-12-2019 |
1644 | Bagasse Power (Malinagar) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Maharashtra | Saswad Mali Sugar Factory Limited | Completed | 80.00 | Not Available | 27-09-2015 |
1645 | Wind Power (Badnagar 79.8 MW) Project* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Madhya Pradesh | Sarjan Realities Limited | Under Construction | 558.60 | 06-Aug-2015 | 21-11-2019 |
1646 | Wind Power (Badnawar-102.9 MW) Project* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Madhya Pradesh | Sarjan Realities Limited | Under Construction | 720.30 | 07-Nov-2014 | 21-11-2019 |
1647 | Wind Power (Khachrod - 35.7MW) Project* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Madhya Pradesh | Sarjan Realities Limited | Under Construction | 249.90 | 03-Jul-2015 | 21-11-2019 |
1648 | Wind Power (Piploda 23.1MW) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Madhya Pradesh | Sarjan Realities Limited | Under Construction | 161.70 | 28-Nov-2015 | 26-02-2016 |
1649 | Kachchh Branch Canal Pumping Station 1 Project | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Irrigation (dams, channels, embankments, etc.) | Gujarat | Sardar Sarovar Narmada Nigam Limited | Completed | 183.47 | 03-Jul-2011 | 04-12-2019 |
1650 | Kachchh Branch Canal Pumping Station 2 & 3 Project | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Irrigation (dams, channels, embankments, etc.) | Gujarat | Sardar Sarovar Narmada Nigam Limited | Completed | 331.26 | 03-Jul-2011 | 04-12-2019 |