List of Infrastructure Projects – State Wise List of Infrastructure Projects – State Wise

This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9243 Total Project Cost(in Rs Crore): 6,813,036.84
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
1591 Bagasse Power (Mulshi) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Shri Sant Tukaram SSK Limited Completed 97.00 Not Available 11-08-2016
1592 Setting up of 5.8 MW solar photovoltaic power unit at Latur Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Shri Saibaba Sugars Limited Completed 50.00 20-Jul-2012 06-06-2019
1593 Expansion of Jamakhandi bagasse based power unit of 35.0 MW in Bagalkot district Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Karnataka Shri Sai Priya Sugar Limites Completed 200.00 31-Dec-2013 09-12-2016
1594 Expansion of bagasse based power unit from 2 MW to 15 MW at Takaliwadi in Kolhapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Shri Gurudatt Sugars Private Limited Completed 110.00 31-Aug-2012 28-11-2016
1595 Bagasse Based Power (Bhende) Project - Expansion* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Shri Dnyaneshwar SSK Limited Under Construction 110.00 Not Available 21-11-2019
1596 Co-generation Power (Dnyaneshwarnagar) Project - Expansion* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Shri Dnyaneshwar SSK Limited Under Construction 100.00 01-Feb-2016 21-11-2019
1597 Bagasse Based Power (Bhavaninagar) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Shri Chhatrapati SSK Limited Completed 72.00 28-Feb-2015 16-08-2019
1598 Setting up of 14 MW bagasse based power unit at Maragur in Vijayapura district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka Shri Bhimashankar SSK Limited Under Construction 56.00 31-Dec-2015 09-11-2016
1599 Churah Valley Hydel Power Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Himachal Pradesh Shri Bajrang Power and Ispat Limited Under Construction 450.00 Not Available 27-09-2015
1600 Setting up of 44 MW bagasse based power unit at Warananagar in Kolhapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Shree Warana SSK Limited Completed 220.00 31-Dec-2009 28-11-2016
1601 38 MW Co-generation Power (Kumathe) Project* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Shree Siddheshwar SSK Limited Under Construction 200.00 10-Jul-2012 21-11-2019
1602 Setting up of 28 MW bagasse based power unit at Devrai in Bid district* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Shree Shambhu Mahadeo Sugar & Allied Industries Limited Pre-construction Stage 128.00 31-Dec-2015 25-10-2019
1603 Setting up of 5 MW solar power unit at Gondri Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Assam Shree Sai Baba Green Power Private Limited Completed 50.00 30-Sep-2012 11-06-2017
1604 Setting up of 15 MW Solar Power unit at Orai in Jalaun district* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Uttar Pradesh Shree Radhey Power & Ispat Private Limited Under Construction 150.00 01-Aug-2016 21-11-2019
1605 Maheshwar Hydel Power Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh Shree Maheshwar Hydel Power Corporation Limited Completed 4,635.00 Not Available 16-08-2019
1606 Wind Power (Sitamau-30 MW) Project* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh Shree Halduni Renewal Energy Private Limited Under Construction 210.00 08-Dec-2015 21-11-2019
1607 Setting up of 10 MW bagasse based power unit at Sohagpur in Betul district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh Shree Durga Khandsari (Sugar) Mills Completed 50.00 26-Aug-2014 09-11-2016
1608 Setting up of coal based power unit & waste heat recovery based power unit at Pedagarlaped in Guntur district* Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Andhra Pradesh Shree Cement Limited Under Construction 140.00 29-Sep-2016 01-11-2019
1609 Setting up of 50 MW captive power unit at Khapradih in Raipur district Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Chhattisgarh Shree Cement Limited Under Construction 200.00 21-Aug-2013 28-11-2016
1610 Setting up of 300 MW coal based power unit at Nardana in Dhule district* Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Maharashtra Shirpur Power Private Limited Under Construction 2,413.00 Not Available 25-10-2019
1611 Development of passenger ropeway from Bypass (TIC)-Lift Mall Road in length of 3.6 Km in Shimla district # Government Infrastructure Projects (PPP) Social and Commercial Infrastructure Tourism Himachal Pradesh Shimla Municipal Corporation Pre-construction Stage 296.67 17-Jun-2015 14-11-2019
1612 Multilevel Parking (Vikasnagar) Project Government Infrastructure Projects (PPP) Transport Urban public transport (except rolling stock) Himachal Pradesh Shimla Municipal Corporation Under Construction 15.00 11-Sep-2012 14-11-2019
1613 Multilevel Parking (Shimla) Project Government Infrastructure Projects (PPP) Transport Urban public transport (except rolling stock) Himachal Pradesh Shimla Municipal Corporation Operation and Maintenance Stage 46.11 28-Feb-2011 20-08-2019
1614 Multilevel Parking (Sanjauli) Project Government Infrastructure Projects (PPP) Transport Urban public transport (except rolling stock) Himachal Pradesh Shimla Municipal Corporation Operation and Maintenance Stage 24.07 04-Feb-2011 14-06-2019
1615 Multilevel Parking (Chotta Shimla) Project Government Infrastructure Projects (PPP) Transport Urban public transport (except rolling stock) Himachal Pradesh Shimla Municipal Corporation Operation and Maintenance Stage 20.00 12-Oct-2010 14-06-2019
1616 Expansion of bagasse based power unit from 3 MW to 30 MW at Chandrapuri in Solapur district* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Shetkari Sakhar Karkhana (Chandrapuri) Limited Under Construction 120.00 01-Nov-2016 21-11-2019
1617 10 MW Latur Solar Power Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Sharda Construction and Corporation Private Limited Completed 60.00 Not Available 10-06-2019
1618 Setting up of 30 MW bagasse based power unit at Kapashi in Satara district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Sharayu Agro Industries Limited Completed 120.00 31-Jan-2016 18-12-2016
1619 Co-generation Power (Narande) Project - Expansion Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Sharad SSK Limited Completed 58.00 Not Available 01-04-2016
1620 Biomass Based Power (Korba) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Chhattisgarh Shanti G D Ispat and Power Private Limited Completed 70.00 Not Available 11-12-2017
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.