List of Infrastructure Projects – State Wise
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
- Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
- Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
- Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
No. of Projects in this Report: | 9243 | Total Project Cost(in Rs Crore): | 6,813,036.84 |
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
1141 | Setting up of 52.5 MW wind power unit at Badnawar in Dhar district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Madhya Pradesh | Suzlon Gujarat Wind Park Limited | Under Construction | 262.50 | 16-Sep-2014 | 18-12-2016 |
1142 | Setting up of 20 MW solar power unit at Saltek & Bhamer in Dhule district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Maharashtra | Suzlon Energy Limited | Completed | 140.00 | 10-Mar-2016 | 20-11-2019 |
1143 | Setting up of 15 MW solar power unit at Kamareddy (Lingapuram) village in Nizamabad district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Telangana | Suzlon Energy Limited | Pre-construction Stage | 120.00 | 29-Feb-2016 | 25-10-2019 |
1144 | Setting up of 18.9 MW wind based power unit at Tallimadugula in Anantapur district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Suzlon Energy Limited | Completed | 94.50 | 31-Oct-2014 | 28-11-2016 |
1145 | Wind Power (Gairatganj) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Madhya Pradesh | Suyog Urja Private Limited | Under Construction | 231.00 | 25-Aug-2014 | 02-03-2016 |
1146 | Wind Power (Sagar) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Madhya Pradesh | Suyog Urja Private Limited | Under Construction | 325.50 | 25-Aug-2014 | 02-03-2016 |
1147 | Coal Based Power (Nagpur) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Maharashtra | Suryalakshmi Cotton Mills | Completed | 220.00 | Not Available | 27-09-2015 |
1148 | Setting up of 10 MW wind power unit at Malusar in Jaisalmer district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Rajasthan | Surya Vidyut Limited | Completed | 59.00 | 24-Jul-2012 | 29-01-2017 |
1149 | Setting up of 14 MW wind power unit at Dangri & Ramsar in Jaisalmer district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Rajasthan | Surya Vidyut Limited | Completed | 84.00 | 14-Mar-2012 | 29-01-2017 |
1150 | Setting up of 50 MW wind power unit at Rojmal in Bhavnagar district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | Surya Vidyut Limited | Under Construction | 250.00 | 10-Aug-2016 | 09-11-2016 |
1151 | 26 MW Wind Power (Surendranagar) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | Surya Vidhyut Limited | Completed | 154.60 | Not Available | 27-09-2015 |
1152 | Setting up of 12 MW coal based power unit at Barahamusa in Sundargarh district | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Odisha | Surendra Mining Industries Private Limited | Completed | 72.00 | 21-Dec-2011 | 06-06-2019 |
1153 | Bridge (Athwa-Adajan) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Gujarat | Surat Municipal Corporation | Completed | 143.64 | 30-Jul-2015 | 04-12-2019 |
1154 | Bridge (Rander-Katargam) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Gujarat | Surat Municipal Corporation | Completed | 190.81 | 21-Oct-2013 | 04-12-2019 |
1155 | BRTS Corridor (Anuvrat Dwar-St. Thomas School-Daksheswar Mahadev Temple) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Urban public transport (except rolling stock) | Gujarat | Surat Municipal Corporation | Under Construction | 58.89 | 18-Sep-2012 | 04-12-2019 |
1156 | BRTS Corridor (Katargam Darwaja-Kosad) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Urban public transport (except rolling stock) | Gujarat | Surat Municipal Corporation | Under Construction | 86.47 | 01-Mar-2013 | 04-12-2019 |
1157 | Flyover (Amroli Junction-Mansarovar Junction) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Gujarat | Surat Municipal Corporation | Completed | 74.62 | 03-Sep-2015 | 04-12-2019 |
1158 | Bridge (Umra & Pal) Project * | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Gujarat | Surat Municipal Corporation | Under Construction | 89.99 | 05-Dec-2015 | 03-12-2019 |
1159 | R-O-B (Bhedwad & Dindoli) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Gujarat | Surat Municipal Corporation | Completed | 82.57 | 20-Sep-2012 | 03-12-2019 |
1160 | Sardar Vallabhbhai Patel River Bridge Project - Modernisation* | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Gujarat | Surat Municipal Corporation | Under Construction | 80.75 | 03-Sep-2015 | 27-11-2019 |
1161 | Implementation of 35 MLD tertiary sewage treatment plant at Bamroli in Surat * | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Sewage collection, treatment and disposal system | Gujarat | Surat Municipal Corporation | Under Construction | 95.00 | 31-Jul-2017 | 25-11-2019 |
1162 | Waste to Power Plant, 1000 TPD, Surat | Government Infrastructure Projects (PPP) | Energy | Electricity generation (grid) | Gujarat | Surat Municipal Corporation | Under Construction | 209.00 | 30-Jun-2012 | 13-11-2019 |
1163 | Flyover (Anuvrat Dwar Junction) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Gujarat | Surat Municipal Corporation | Completed | 64.36 | 05-Sep-2014 | 07-10-2019 |
1164 | High-Tech Amusement Park (Surat) Project | Government Infrastructure Projects (PPP) | Social and Commercial Infrastructure | Tourism | Gujarat | Surat Municipal Corporation | Operation and Maintenance Stage | 228.77 | 31-Jul-2012 | 13-09-2019 |
1165 | Flyover (Katargam) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Gujarat | Surat Municipal Corporation | Completed | 63.34 | 18-Sep-2012 | 03-07-2019 |
1166 | Bridge (Kapodra-Utran) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Gujarat | Surat Municipal Corporation | Completed | 77.14 | 16-Oct-2009 | 02-07-2019 |
1167 | Bridge (Tapi River) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Gujarat | Surat Municipal Corporation | Completed | 67.80 | 09-Aug-2012 | 02-07-2019 |
1168 | Flyover (Delhi Gate, Amisha Hotel & Darwaja Junction) Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Gujarat | Surat Municipal Corporation | Completed | 100.36 | 06-Sep-2012 | 02-07-2019 |
1169 | MSW Processing Plant at Khajod | Government Infrastructure Projects (PPP) | Water Sanitation | Solid waste management | Gujarat | Surat Municipal Corporation | Operation and Maintenance Stage | 50.00 | Not Available | 03-12-2018 |
1170 | Setting up of 8.4 MW wind power unit at Bhanvad | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | Surat Municipal Corporation | Completed | 58.80 | 05-Oct-2012 | 09-11-2017 |