List of Infrastructure Projects – State Wise
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
- Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
- Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
- Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
No. of Projects in this Report: | 9243 | Total Project Cost(in Rs Crore): | 6,813,036.84 |
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
811 | Implementation of water supply scheme in Alwar | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Water supply pipeline | Rajasthan | Urban Development and Housing Department, Rajasthan | Completed | 57.68 | 23-Jun-2008 | 06-03-2017 |
812 | Construction of flyover at Maharana Pratap chowk in length of 1.6 km | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Chhattisgarh | Urban Administration & Development, Chhattisgarh | Completed | 65.77 | Not Available | 25-10-2019 |
813 | IT Special Economic Zone (Kozhikode) [UL Cyber Park] Project - Phase I | Government Infrastructure Projects (Traditional Procurement) | Social and Commercial Infrastructure | Common infrastructure for industrial parks, SEZ | Kerala | Uralungal Labour Contract Co-operative Society | Completed | 270.00 | 10-Apr-2012 | 14-04-2016 |
814 | Wind Power (Badnagar and Badnawar - 60 MW) Project* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Madhya Pradesh | Uppaluru Power Projects Private Limited | Under Construction | 420.00 | 05-Nov-2015 | 21-11-2019 |
815 | Development of an industrial park on 79.1 acres at Hansalpura* | Government Infrastructure Projects (Traditional Procurement) | Social and Commercial Infrastructure | Common infrastructure for industrial parks, SEZ | Gujarat | Universal Industrial Park LLP | Under Construction | 164.00 | 31-Jan-2017 | 25-10-2019 |
816 | Setting up of 5 MW solar photovoltaic power unit at Khirasara | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | Unity Power Private Limited | Completed | 50.00 | Not Available | 11-06-2017 |
817 | Wind Power (Sitamau-67.5 MW) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Madhya Pradesh | Unique Construction, Kayathar | Under Construction | 472.50 | 25-Aug-2014 | 02-03-2016 |
818 | Implementation of water supply scheme at Ulhasnagar in Thane district under JNNURM district | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Water supply pipeline | Maharashtra | Ulhasnagar Municipal Corporation | Completed | 265.00 | 19-Dec-2008 | 04-12-2019 |
819 | Implementation of 120 MW hydel power unit at Vyasi# | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | UJVN Limited | Under Construction | 936.23 | 20-Jan-2014 | 04-12-2019 |
820 | Hydel Power Project (Phata-Byung)#* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | UJVN Limited | Under Construction | 484.00 | 01-Jun-2014 | 03-12-2019 |
821 | Renovation of existing 41.4 MW Khatima hydel power project in Udham Singh Nagar district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | UJVN Limited | Under Construction | 256.77 | 03-Jan-2012 | 09-11-2019 |
822 | Sarju Hydel Power Project - Stage II | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | UJVN Limited | Completed | 91.49 | Not Available | 22-07-2019 |
823 | Sarju Hydel Power Project - Stage III | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | UJVN Limited | Completed | 65.80 | Not Available | 22-07-2019 |
824 | Bhilangana II A hydro project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | UJVN Limited | Under Construction | 233.81 | 18-Sep-2012 | 06-03-2017 |
825 | Hydel Power (Madmaheshwar) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | UJVN Limited | Under Construction | 194.52 | 01-Dec-2015 | 06-03-2017 |
826 | Hydel Power Project (Bgyunder Ganga) | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | UJVN Limited | Under Construction | 137.69 | Not Available | 06-03-2017 |
827 | Hydel Power Project (Jhala Koti) | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | UJVN Limited | Under Construction | 80.57 | Not Available | 06-03-2017 |
828 | Hydel Power Project (Srinagar) | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | UJVN Limited | Completed | 4,192.00 | Not Available | 06-03-2017 |
829 | Kaliganga-II Small Hydro Power Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | UJVN Limited | Under Construction | 65.94 | 18-Nov-2015 | 06-03-2017 |
830 | Renovation of existing 20.4 MW Pathri hydel power project in Haridwar district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | UJVN Limited | Completed | 113.25 | 09-Mar-2010 | 09-11-2016 |
831 | 25 MW Solar Photovoltaic Power (Surendranagar) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | Ujjawala Power Private Limited | Completed | 200.00 | Not Available | 27-09-2015 |
832 | Setting up of 15.5 MW solar power unit at Halhipura | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Madhya Pradesh | Ujaas Energy Limited | Completed | 155.00 | Not Available | 11-06-2017 |
833 | Setting up of 23 MW solar power unit at Khetakhedi | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Madhya Pradesh | Ujaas Energy Limited | Completed | 230.00 | Not Available | 11-06-2017 |
834 | Setting up of 28.8 MW solar power unit at Bardodi | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Madhya Pradesh | Ujaas Energy Limited | Completed | 287.50 | Not Available | 11-06-2017 |
835 | Solar Power (Kakdel) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Madhya Pradesh | Ujaas Energy Limited | Completed | 110.00 | 28-Mar-2013 | 03-10-2016 |
836 | Solar Photovoltaic Power (Gagroni) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Madhya Pradesh | Ujaas Energy Limited | Completed | 100.00 | Not Available | 05-01-2016 |
837 | Implementation of 20 MLD sewage treatment plant at Udaipur | Government Infrastructure Projects (PPP) | Water Sanitation | Sewage collection, treatment and disposal system | Rajasthan | Udaipur Municipal Corporation | Operation and Maintenance Stage | 20.00 | 09-May-2012 | 21-06-2019 |
838 | Useful Conversion of Solid Waste in Udaipur | Government Infrastructure Projects (PPP) | Water Sanitation | Solid waste management | Rajasthan | Udaipur Municipal Corporation | Operation and Maintenance Stage | 70.00 | Not Available | 09-11-2015 |
839 | Bagasse Power (Ajani) Project* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Maharashtra | Twentyone Sugars Limited | Under Construction | 380.00 | Not Available | 21-11-2019 |
840 | Wind Based Power (Khatav) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Maharashtra | TVS Energy Limited | Completed | 178.00 | Not Available | 02-11-2015 |