List of Infrastructure Projects – State Wise List of Infrastructure Projects – State Wise

This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9243 Total Project Cost(in Rs Crore): 6,813,036.84
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
511 Ring Road Project (Bathinda) Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges Punjab Bathinda Development Authority Completed 51.63 24-Jun-2010 01-07-2019
512 Setting up of 20 MW solar based power unit at Jambalapuram in Madurai district* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu Bee Solar Energy Private Limited Pre-construction Stage 130.00 01-Apr-2016 25-10-2019
513 Wind Power (Sironj) Project* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh Begusarai Biomass Private Limited Under Construction 700.00 07-Nov-2014 21-11-2019
514 Development of 7 MLD water supply project at Bekal Kasargod Dist * Government Infrastructure Projects (PPP) Water Sanitation Water supply pipeline Kerala Bekal Resorts Development Corporation Limited Under Construction 17.00 Not Available 09-11-2019
515 Development of resorts at Bekal in Kasaragod District * Government Infrastructure Projects (PPP) Social and Commercial Infrastructure Tourism Kerala Bekal Resorts Development Corporation Limited Under Construction 55.00 Not Available 09-11-2019
516 Development of Integrated Solid Waste Treatment (100 TPD) and Landfill Facilities at Belgaum * Government Infrastructure Projects (PPP) Water Sanitation Solid waste management Karnataka Belagavi City Corporation Under Construction 5.12 18-Jun-2007 09-11-2019
517 40 MW Solar Power (Nataram) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh Belectric Photovoltaic India Private Limited Completed 400.00 09-Sep-2015 03-10-2016
518 Setting up of 14 MW co-generation power unit at Hudali in Belagavi district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka Belgaum Sugars Private Limited Under Construction 59.12 19-Nov-2015 05-12-2016
519 Tornagallu Truck Terminal * Government Infrastructure Projects (PPP) Transport Urban public transport (except rolling stock) Karnataka Bellary Urban Development Authority (BUDA) Pre-construction Stage 29.00 Not Available 08-11-2019
520 Construction of ring road in length of 18 km in Bellary Government Infrastructure Projects (PPP) Transport Roads and bridges Karnataka Bellary Urban Development Authority (BUDA) Operation and Maintenance Stage 90.00 02-Mar-2009 09-08-2019
521 Implementation of Drinking Water Supply Scheme at Berhampur in Ganjam district* Government Infrastructure Projects (Traditional Procurement) Water Sanitation Water supply pipeline Odisha Berhampur Municipal Corporation Under Construction 471.98 17-Oct-2016 03-12-2019
522 Setting up of 12 MW rice husk based power unit in Bhojpur district* Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Bihar Bermaco Energy Systems Limited Under Construction 60.00 31-Dec-2015 25-10-2019
523 Combined Cycle Gas Based Power (Nand Nagar Industrial Area) Project Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Uttarakhand Beta Infratech Private Limited Completed 845.96 30-May-2011 03-10-2016
524 Setting up of 43.2 MW wind power unit at Kadavakallu in Anantapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Beta Wind Farm Private Limited Completed 302.40 28-Feb-2011 11-01-2017
525 Setting up of 7.2 MW wind power unit at Kadavakallu in Anantapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Beta Wind Farm Private Limited Completed 50.40 22-Aug-2012 11-01-2017
526 50.8 MW Wind Power (Jamanwada) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Beta Wind Farm Private Limited Completed 312.00 Not Available 17-11-2015
527 10.5 MW Wind Power (Kutch) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Beta Wind Farm Private Limited Completed 63.00 Not Available 27-09-2015
528 Wind Power (Tadapatri) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Beta Wind Farm Private Limited Completed 588.00 Not Available 27-09-2015
529 Wind Power (Tirunelveli) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu Beta Wind Farm Private Limited Completed 965.00 Not Available 27-09-2015
530 Wind Power (Bhainsdehi) Project* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh Betul Wind Farm Limited Under Construction 350.00 10-Dec-2014 21-11-2019
531 Wind Power (Dangri) Project - Phase II* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan BG Wind Power Limited Under Construction 100.00 30-Nov-2014 21-11-2019
532 Implementation of 20 MW wind based power unit at Kodiyasar - BG Wind Power Limited Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan BG Wind Power Limited Completed 120.00 31-May-2016 08-11-2017
533 Waste Immobilisation (Trombay, Kalpakkam & Tarapur) Project Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Multi State/ Centre Bhabha Atomic Research Centre (BARC) Completed 0.00 Not Available 02-07-2019
534 Solar Power (Bid) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh Bhadresh Trading Corporation Limited Under Construction 70.00 Not Available 10-06-2019
535 Setting up of 30 MW solar power unit at Kombhalne Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Bhageria Industries Limited Completed 210.00 10-Mar-2016 06-06-2019
536 City Gas Distribution (Hyderabad & Vijayawada) Project* Government Infrastructure Projects (Traditional Procurement) Energy City gas distribution Multi State/ Centre Bhagyanagar Gas Limited Under Construction 0.00 Not Available 25-11-2019
537 Bhakra Left Bank Power Project - Expansion Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Punjab Bhakra Beas Management Board Completed 490.00 Not Available 03-12-2019
538 Bhakra Right Bank Project - Expansion Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Punjab Bhakra Beas Management Board Completed 0.00 Not Available 27-09-2015
539 Setting up of 31.5 MW Solar Power unit at Mirpur Lalan in Mansa district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Punjab Bhanu Energy Infrastructure & Power Limited Completed 200.00 30-Jun-2014 31-10-2016
540 Setting up of 15 MW biomass based power unit at Piduru in Nellore district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Bhanu Prakash Power Projects Private Limited Completed 75.00 28-Feb-2011 28-11-2016
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.