List of Infrastructure Projects – State Wise List of Infrastructure Projects – State Wise

This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9243 Total Project Cost(in Rs Crore): 6,813,036.84
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
931 Implementation of Gunjimunda & Pandkimal mega lift irrigation schemes on 5930.5 acres of land Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Odisha Water Resources Department, Odisha Completed 72.06 06-Aug-2013 29-11-2019
932 Implementation of Gurujibhata, Dunguripali & Bhuskimal mega lift irrigation schemes on 10378.4 acres of land Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Odisha Water Resources Department, Odisha Completed 61.19 06-Aug-2013 29-11-2019
933 Implementation of Haripur mega lift irrigation scheme on 1729.74 acres of land Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Odisha Water Resources Department, Odisha Completed 57.84 26-Dec-2016 29-11-2019
934 Implementation of Jangala & Biritola mega lift irrigation schemes on 6177.6 acres of land Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Odisha Water Resources Department, Odisha Completed 57.33 21-Dec-2015 29-11-2019
935 Implementation of Jankdihi & Sairha mega lift irrigation schemes on 8154.5 acres of land Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Odisha Water Resources Department, Odisha Completed 65.35 08-Mar-2015 29-11-2019
936 Implementation of Katikula mega lift irrigation scheme on 1976.8 acres of land Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Odisha Water Resources Department, Odisha Completed 64.36 08-Mar-2015 29-11-2019
937 Implementation of Kudabaga mega lift irrigation scheme on 1235.5 acres of land Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Odisha Water Resources Department, Odisha Completed 102.98 08-Mar-2015 29-11-2019
938 Implementation of Kulsara & Bhulkabahal mega lift irrigation schemes on 6795.4 acres of land Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Odisha Water Resources Department, Odisha Completed 54.05 21-Dec-2015 29-11-2019
939 Implementation of Kusumura mega lift irrigation scheme on 1235.53 acres of land Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Odisha Water Resources Department, Odisha Completed 119.00 26-Dec-2016 29-11-2019
940 Implementation of Laitara mega lift irrigation scheme on 1235.53 acres of land Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Odisha Water Resources Department, Odisha Completed 52.45 06-Aug-2013 29-11-2019
941 Implementation of lift irrigation scheme on 254624.8 acres in Kustagi, Yelburga and Gangavathi in Koppal Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Karnataka Krishna Bhagya Jala Nigam Limited Completed 7,769.46 24-Feb-2014 29-11-2019
942 Implementation of Madhabarida & Kalingadola mega lift irrigation schemes on 4447.9 acres of land Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Odisha Water Resources Department, Odisha Completed 89.99 26-Dec-2016 29-11-2019
943 Implementation of Mahajanpara & Brahmnipal mega lift irrigation schemes on 6918.9 acres of land Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Odisha Water Resources Department, Odisha Completed 67.25 06-Aug-2013 29-11-2019
944 Implementation of Mahan Irrigation project on 49853.5 acres Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Madhya Pradesh Water Resources Department, Madhya Pradesh Completed 486.96 10-Sep-2015 29-11-2019
945 Implementation of Nuagaon & Chandnimal mega lift irrigation schemes on 8648.7 acres of land Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Odisha Water Resources Department, Odisha Completed 60.07 08-Mar-2015 29-11-2019
946 Implementation of Patapur mega lift irrigation scheme on 1927.42 acres of land Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Odisha Water Resources Department, Odisha Completed 51.92 26-Dec-2016 29-11-2019
947 Implementation of Rajapur, Rahapada & Tulsipur mega lift irrigation schemes on 10872.6 acres of land Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Odisha Water Resources Department, Odisha Completed 72.18 21-Dec-2015 29-11-2019
948 Implementation of Rampila-I & Rampila-II mega lift irrigation schemes on 7907.4 acres of land Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Odisha Water Resources Department, Odisha Completed 64.61 08-Mar-2015 29-11-2019
949 Implementation of Redama & Balma mega lift irrigation schemes on 8648.7 acres of land Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Odisha Water Resources Department, Odisha Completed 60.41 26-Dec-2016 29-11-2019
950 Implementation of Renkuli mega lift irrigation scheme on 1235.5 acres of land Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Odisha Water Resources Department, Odisha Completed 102.97 08-Mar-2015 29-11-2019
951 Implementation of rural electrification works in Aska & Bhanjanagar under Integrated Power Development Scheme Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Odisha Odisha Power Transmission Corporation Limited Completed 71.19 20-Jul-2016 29-11-2019
952 Implementation of rural electrification works in Betul under DDUGJY Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Madhya Pradesh Madhya Pradesh Madhya Kshetra Vidyut Vitaran Company Limited Completed 144.74 28-Dec-2016 29-11-2019
953 Implementation of rural electrification works in EDC Allahabad I & II under Integrated Power Development Scheme Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Uttar Pradesh Purvanchal Vidyut Vitran Nigam Limited Completed 51.27 20-Aug-2016 29-11-2019
954 Implementation of rural electrification works in EDC Mau, Sonbhadra & Azamgarh under Integrated Power Development Scheme Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Uttar Pradesh Purvanchal Vidyut Vitran Nigam Limited Completed 76.54 20-Aug-2016 29-11-2019
955 Implementation of rural electrification works in EDC Mirzapur, Deoria & Gorakhpur under Integrated Power Development Scheme Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Uttar Pradesh Purvanchal Vidyut Vitran Nigam Limited Completed 76.33 20-Aug-2016 29-11-2019
956 Implementation of rural electrification works in EDC Varanasi, Fatehpur & Gazipur under Integrated Power Development Scheme Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Uttar Pradesh Purvanchal Vidyut Vitran Nigam Limited Completed 75.44 20-Aug-2016 29-11-2019
957 Implementation of rural electrification works in EUDC Allahabad under Integrated Power Development Scheme Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Uttar Pradesh Purvanchal Vidyut Vitran Nigam Limited Completed 250.03 20-Aug-2016 29-11-2019
958 Implementation of rural electrification works in EUDC Gorakhpur under Integrated Power Development Scheme Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Uttar Pradesh Purvanchal Vidyut Vitran Nigam Limited Completed 118.38 20-Aug-2016 29-11-2019
959 Implementation of rural electrification works in Jalgaon under RAPDRP-Part B Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Maharashtra Maharashtra State Electricity Distribution Company Limited Completed 93.62 19-Jan-2012 29-11-2019
960 Implementation of rural electrification works in Kalyan under RAPDRP-Part B Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Maharashtra Maharashtra State Electricity Distribution Company Limited Completed 93.77 19-Jan-2012 29-11-2019
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.