List of Infrastructure Projects – State Wise List of Infrastructure Projects – State Wise

This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9243 Total Project Cost(in Rs Crore): 6,813,036.84
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
1561 Implementation of 220 kV substation at Baram Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Uttarakhand Power Transmission Corporation of Uttarakhand Limited Under Construction 120.84 31-Dec-2015 12-01-2017
1562 Implementation of Chheligada irrigation scheme 43.2 CBM Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Odisha Water Resources Department, Odisha Under Construction 207.01 30-Jun-2004 12-01-2017
1563 Implementation of Kanupur irrigation scheme with a capacity of 33.1 CBM Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Odisha Water Resources Department, Odisha Under Construction 1,801.25 31-Dec-2004 12-01-2017
1564 Implementation of Lower Suktel irrigation scheme spread over 56834.2 acres of land Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Odisha Water Resources Department, Odisha Under Construction 1,041.81 31-Dec-2000 12-01-2017
1565 Implementation of Manjore irrigation scheme spread over 14826.3 acres of land Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Odisha Water Resources Department, Odisha Under Construction 226.77 31-Dec-1997 12-01-2017
1566 Implementation of Rengali right bank canal with a capacity of 314.2 CBM Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Odisha Water Resources Department, Odisha Under Construction 1,962.33 31-Mar-1998 12-01-2017
1567 Implementation of rural electrification works in Kokrajhar district under RGGVY XIth Plan Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Assam Assam Power Distribution Company Limited Completed 67.30 28-Feb-2009 12-01-2017
1568 Implementation of Varuna corridor irrigation scheme of 10.3 Km in Varanasi district Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Uttar Pradesh Irrigation Department, Uttar Pradesh Under Construction 201.65 27-Mar-2016 12-01-2017
1569 Laying of Srinagar-Satpulli transmission line in length of 52.4 CKM Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Uttarakhand Power Transmission Corporation of Uttarakhand Limited Completed 55.33 16-Aug-2004 12-01-2017
1570 Setting up a 10 MW captive waste heat recovery power unit in Ballari district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka Rayen Steel Private Limited Under Construction 50.00 15-Dec-2016 12-01-2017
1571 Setting up of 50 MW solar power unit at Kurdi in Raichur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka Parampujya Solar Energy Private Limited Under Construction 410.00 02-Jul-2016 12-01-2017
1572 Setting up of 10 MW solar power unit at Honnali Rural in Devangere district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka J K Petroenergy Private Limited Under Construction 116.00 02-Jul-2016 12-01-2017
1573 Setting up of 10 MW solar power unit at Kesinga in Kalahandi district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Odisha Jyoti Infrastructure Private Limited Under Construction 105.00 22-Nov-2016 12-01-2017
1574 Setting up of 10 MW solar power unit at Kudri Kotgi in Koppal district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka Parampujya Solar Energy Private Limited Under Construction 99.00 02-Jul-2016 12-01-2017
1575 Setting up of 10.5 MW wind power unit at Tirumalayapali in Kadapa district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Hetero Wind Power Limited Completed 73.50 20-Jan-2014 12-01-2017
1576 Setting up of 10.5 MW wind power unit at Vajrakarur in Anantapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Indian Oil Corporation Limited Completed 73.50 31-Dec-2009 12-01-2017
1577 Setting up of 100 MW wind power unit at Tagguparthi & Beluguppa in Anantapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Energon Power Resources Private Limited Completed 700.00 12-Sep-2012 12-01-2017
1578 Setting up of 12.8 MW wind power unit at Chinnakolumalapalli in Kurnool district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Danu Wind Parks Private Limited Completed 89.60 08-Mar-2014 12-01-2017
1579 Setting up of 14.7 MW wind power unit at Gandikota in Kadapa district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Indian Oil Corporation Limited Completed 102.90 04-Nov-2010 12-01-2017
1580 Setting up of 16.0 MW wind power unit at Talaricheruvu in Anantapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh ZR Renewable Energy Private Limited Completed 112.00 28-Feb-2014 12-01-2017
1581 Setting up of 16.8 MW wind power unit at Pottipadu & Vajrakarur in Anantapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Mytrah Vayu (Indravathi) Private Limited Completed 117.60 27-Oct-2013 12-01-2017
1582 Setting up of 17.0 MW wind power unit at Gangadevipalli in Kadapa district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Atria Wind Power Private Limited Completed 119.00 16-Mar-2014 12-01-2017
1583 Setting up of 18.7 MW wind power unit at Molagavalli in Kurnool district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh KCT Renewable Energy Private Limited Completed 130.90 30-Jan-2014 12-01-2017
1584 Setting up of 20 MW solar power unit at Sadipali in Balangir district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Odisha IBC Solar Ventures India B.V. Under Construction 172.00 22-Nov-2016 12-01-2017
1585 Setting up of 20.4 MW wind power unit at Molagavalli in Kurnool district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh KCT Renewable Energy Private Limited Completed 142.80 15-Jan-2014 12-01-2017
1586 Setting up of 21.0 MW wind power unit at Elutla & Madugupalli in Anantapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh ReNew Wind Energy (Shivpur) Private Limited Completed 157.50 09-May-2014 12-01-2017
1587 Setting up of 21.0 MW wind power unit at Pottipadu & Vajrakarur in Anantapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Mytrah Vayu (Indravathi) Private Limited Completed 147.00 29-Sep-2013 12-01-2017
1588 Setting up of 23.1 MW wind power unit at Elutla in Anantapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh ReNew Wind Energy (Shivpur) Private Limited Completed 161.70 30-Mar-2014 12-01-2017
1589 Setting up of 23.1 MW wind power unit at Pottipadu & Vajrakarur in Anantapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Mytrah Vayu (Indravathi) Private Limited Completed 161.70 29-Jun-2013 12-01-2017
1590 Setting up of 24.0 MW wind power unit at Idukal in Anantapur district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Poly Solar Parks Private Limited Completed 181.00 17-Jan-2014 12-01-2017
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.