List of Infrastructure Projects – State Wise
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
- Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
- Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
- Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
No. of Projects in this Report: | 9243 | Total Project Cost(in Rs Crore): | 6,813,036.84 |
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
1531 | Setting up of 40 MW solar power unit at Ittagi in Bellary district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Karnataka | Hero Solar Energy Private Limited | Under Construction | 336.00 | 02-Jul-2016 | 11-01-2017 |
1532 | Setting up of 40 MW solar power unit at Kadala in Dhenkanal district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Odisha | Essel Green Energy Private Limited | Under Construction | 323.00 | 22-Nov-2016 | 11-01-2017 |
1533 | Setting up of 40 MW solar power unit at Ranna-Belagali in Bagalkot district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Karnataka | Acme Solar Holdings Private Limited | Under Construction | 400.00 | 02-Jul-2016 | 11-01-2017 |
1534 | Setting up of 40 solar power unit at Ghataprabha in Belgaum district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Karnataka | Acme Solar Holdings Private Limited | Under Construction | 280.00 | 02-Jul-2016 | 11-01-2017 |
1535 | Setting up of 42.0 MW wind power unit at Vajrakarur in Anantapur district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Mytrah Vayu (Pennar) Private Limited | Completed | 294.00 | 30-Apr-2009 | 11-01-2017 |
1536 | Setting up of 43.2 MW wind power unit at Kadavakallu in Anantapur district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Beta Wind Farm Private Limited | Completed | 302.40 | 28-Feb-2011 | 11-01-2017 |
1537 | Setting up of 48.0 MW wind power unit at Tagguparthi in Anantapur district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Energon Power Resources Private Limited | Completed | 336.00 | 30-Jun-2012 | 11-01-2017 |
1538 | Setting up of 7.2 MW wind power unit at Kadavakallu in Anantapur district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Beta Wind Farm Private Limited | Completed | 50.40 | 22-Aug-2012 | 11-01-2017 |
1539 | Setting up of 8.0 MW wind power unit at Balavenkatapuram in Anantapur district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Rayala Wind Power Company Private Limited | Completed | 56.70 | 16-Mar-2013 | 11-01-2017 |
1540 | Setting up of 8.0 MW wind power unit at Kalyandurg in Anantapur district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Blyth Wind Park Private Limited | Completed | 57.00 | 30-Jun-2013 | 11-01-2017 |
1541 | Setting up of 8.0 MW wind power unit at Nallakonda in Anantapur district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Vish Wind Infrastructure LLP | Completed | 56.00 | 01-Feb-2009 | 11-01-2017 |
1542 | Setting up of 8.0 MW wind power unit at Nallakonda in Anantapur district - Phase V | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Khandke Wind Energy Private Limited | Completed | 56.00 | 24-Apr-2011 | 11-01-2017 |
1543 | Setting up of 8.0 MW wind power unit at Nallakonda in Anantapur district - Phase VI | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Khandke Wind Energy Private Limited | Completed | 60.00 | 30-Jun-2011 | 11-01-2017 |
1544 | Setting up of 8.4 MW wind power unit at Tallimadugula in Anantapur district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | KRBL Limited | Completed | 60.48 | 31-May-2012 | 11-01-2017 |
1545 | Setting up of 8.4 MW wind power unit at Vajrakarur in Anantapur district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Mytrah Vayu (Pennar) Private Limited | Completed | 58.80 | 31-Dec-2009 | 11-01-2017 |
1546 | Setting up of 80 MW solar power unit at Ambosara in Jajpur district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Odisha | Essel Green Energy Private Limited | Under Construction | 721.00 | 22-Nov-2016 | 11-01-2017 |
1547 | Setting up of 80 MW solar power unit at Vajramatti in Bagalkot district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Karnataka | Acme Solar Holdings Private Limited | Under Construction | 560.00 | 02-Jul-2016 | 11-01-2017 |
1548 | Setting up of 9.6 MW wind power unit at Nallakonda in Anantapur district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Tadas Wind Energy Limited | Completed | 67.20 | 16-Feb-2009 | 11-01-2017 |
1549 | Setting up of solar power unit at Parashuramadevara Kote in Chitradurga district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Karnataka | Hero Solar Energy Private Limited | Under Construction | 210.00 | 02-Jul-2016 | 11-01-2017 |
1550 | Two laning of 24.6 Km carriageway and four laning of 2.0 Km carriageway of NH-353 in Nuapada district | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Odisha | Public Works Department, Odisha | Under Construction | 51.22 | 18-Sep-2015 | 11-01-2017 |
1551 | Upgradation of Amritsar bypass in length of 24.6 Km in Amritsar district | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Punjab | National Highways Authority of India (NHAI) | Under Construction | 273.06 | 30-Nov-2015 | 11-01-2017 |
1552 | Upgradation of Harishchandrapur-Kalindri Bridge in length of 12.6 Km | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | West Bengal | Public Works Department, West Bengal | Under Construction | 291.20 | 02-Nov-2016 | 11-01-2017 |
1553 | Upgradation of Kishanganj-Bahadurganj road & Bahadurganj-Terhagachh road in length of 34.0 Km in Kishanganj district | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Bihar | Road Construction Department, Bihar | Under Construction | 54.02 | 28-Feb-2014 | 11-01-2017 |
1554 | Upgradation of various roads in length of 38.6 Km in Darbhanga district | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Bihar | Road Construction Department, Bihar | Completed | 53.57 | 21-Jan-2013 | 11-01-2017 |
1555 | Water Sports & FEC at Rajahmundry | Government Infrastructure Projects (PPP) | Social and Commercial Infrastructure | Tourism | Andhra Pradesh | Andhra Pradesh Tourism Development Corporation Limited | Operation and Maintenance Stage | 12.00 | 30-Apr-2004 | 11-01-2017 |
1556 | Construction of Hamirpur bypass in length of 6.4 Km of NH-88 | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Himachal Pradesh | Public Works Department, Himachal Pradesh | Completed | 75.00 | 31-Mar-2010 | 12-01-2017 |
1557 | Construction of mega food park at Ladhowal in Ludhiana district | Government Infrastructure Projects (Traditional Procurement) | Social and Commercial Infrastructure | Common infrastructure for industrial parks, SEZ | Punjab | Punjab Agro Industries Corporation Limited | Under Construction | 117.61 | 30-Oct-2016 | 12-01-2017 |
1558 | Construction of two lane 2 way flyover of 1.3 Km on Ashram Road in Ahmedabad district | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Gujarat | Ahmedabad Municipal Corporation | Under Construction | 86.46 | 30-Jun-2016 | 12-01-2017 |
1559 | Development of multi-modal IWT terminal with a capacity of 7.9 MMTPA at Haldia in Purba Medinipur district | Government Infrastructure Projects (Traditional Procurement) | Transport | Inland waterways | West Bengal | Inland Waterways Authority of India | Pre-construction Stage | 517.00 | 30-Dec-2016 | 12-01-2017 |
1560 | Implementation of Subarnarekha irrigation scheme spread over 165560.6 acres of land | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Irrigation (dams, channels, embankments, etc.) | Odisha | Water Resources Department, Odisha | Under Construction | 3,898.44 | 31-Dec-1996 | 12-01-2017 |