This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
- Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
- Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
- Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
No. of Projects in this Report: | 9243 | Total Project Cost(in Rs Crore): | 6,813,036.84 |
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
1141 | Wind Power (Kalyandurg) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Karam Chand Thapar & Bros. (Coal Sales) Limited | Completed | 165.00 | 31-Dec-2014 | 03-10-2016 |
1142 | Wind Power (Khandke) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Maharashtra | Lalpur Wind Energy Private Limited | Completed | 532.00 | 24-Feb-2015 | 03-10-2016 |
1143 | Rural Electrification (Arwal) - RGGVY 12th Plan | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Bihar | South Bihar Power Distribution Company Limited | Under Construction | 59.60 | 26-Feb-2015 | 17-10-2016 |
1144 | Rural Electrification (Bangalore) Project - R-APDRP | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Karnataka | Bangalore Electricity Supply Company Limited | Completed | 431.01 | 11-Dec-2009 | 17-10-2016 |
1145 | Rural Electrification (Bhagalpur) - RGGVY 12th Plan | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Bihar | South Bihar Power Distribution Company Limited | Under Construction | 247.53 | 01-Dec-2014 | 17-10-2016 |
1146 | Rural Electrification (Buxar) - RGGVY 12th Plan | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Bihar | South Bihar Power Distribution Company Limited | Under Construction | 203.70 | 03-Nov-2014 | 17-10-2016 |
1147 | Rural Electrification (Jamui) - RGGVY 12th Plan | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Bihar | South Bihar Power Distribution Company Limited | Under Construction | 220.96 | 01-Oct-2014 | 17-10-2016 |
1148 | Rural Electrification (Kaimur) - RGGVY 12th Plan | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Bihar | South Bihar Power Distribution Company Limited | Under Construction | 194.21 | 15-Oct-2014 | 17-10-2016 |
1149 | Rural Electrification (Lakhisarai) - RGGVY 12th Plan | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Bihar | South Bihar Power Distribution Company Limited | Under Construction | 113.28 | 17-Mar-2015 | 17-10-2016 |
1150 | Rural Electrification (Munger) - RGGVY 12th Plan | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Bihar | South Bihar Power Distribution Company Limited | Under Construction | 136.50 | 13-Oct-2014 | 17-10-2016 |
1151 | Rural Electrification (Raisen) - RGGVY | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Madhya Pradesh | Madhya Pradesh Madhya Kshetra Vidyut Vitaran Company Limited | Under Construction | 57.79 | 07-Jan-2015 | 17-10-2016 |
1152 | Rural Electrification (Sheikhpura & Jehanabad) - RGGVY 12th Plan | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Bihar | South Bihar Power Distribution Company Limited | Under Construction | 134.29 | 06-Feb-2015 | 17-10-2016 |
1153 | Power Transmission (Barpeta) Project - RGGVY | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Assam | Assam Power Distribution Company Limited | Completed | 146.50 | 09-Jan-2009 | 18-10-2016 |
1154 | Power Transmission (Cachar) Project - RGGVY | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Assam | Assam Power Distribution Company Limited | Completed | 74.62 | 05-Mar-2007 | 18-10-2016 |
1155 | Power Transmission (Darrang) Project - RGGVY | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Assam | Assam Power Distribution Company Limited | Completed | 164.10 | 24-Sep-2008 | 18-10-2016 |
1156 | Power Transmission (Dhubri) Project - RGGVY | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Assam | Assam Power Distribution Company Limited | Completed | 184.64 | 09-Jan-2009 | 18-10-2016 |
1157 | Power Transmission (Dibrugarh) Project - RGGVY | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Assam | Assam Power Distribution Company Limited | Completed | 100.42 | 06-Feb-2009 | 18-10-2016 |
1158 | Power Transmission (Golaghat) Project - RGGVY | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Assam | Assam Power Distribution Company Limited | Completed | 109.08 | 16-Sep-2008 | 18-10-2016 |
1159 | Power Transmission (Jorhat) Project - RGGVY | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Assam | Assam Power Distribution Company Limited | Completed | 84.65 | 16-Jun-2008 | 18-10-2016 |
1160 | Power Transmission (Kamrup) Project - RGGVY | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Assam | Assam Power Distribution Company Limited | Completed | 199.28 | 16-Feb-2009 | 18-10-2016 |
1161 | Power Transmission (Karbi Anglong) Project - RGGVY | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Assam | Assam Power Distribution Company Limited | Completed | 458.83 | 30-Jan-2009 | 18-10-2016 |
1162 | Power Transmission (Karimganj) Project - RGGVY | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Assam | Assam Power Distribution Company Limited | Completed | 59.85 | 14-May-2009 | 18-10-2016 |
1163 | Power Transmission (Kharadpada) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Dadra & Nagar Haveli (UT) | DNH Power Distribution Corporation Limited | Under Construction | 50.00 | 01-Mar-2015 | 18-10-2016 |
1164 | Power Transmission (Lakhimpur) Project - RGGVY | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Assam | Assam Power Distribution Company Limited | Completed | 132.45 | 02-Mar-2009 | 18-10-2016 |
1165 | Power Transmission (Morigaon) Project - RGGVY | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Assam | Assam Power Distribution Company Limited | Completed | 62.18 | 09-Jun-2008 | 18-10-2016 |
1166 | Power Transmission (Nagaon) Project - RGGVY | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Assam | Assam Power Distribution Company Limited | Completed | 158.44 | 08-Jan-2009 | 18-10-2016 |
1167 | Power Transmission (Nalbari) Project - RGGVY | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Assam | Assam Power Distribution Company Limited | Completed | 84.44 | 14-Jun-2008 | 18-10-2016 |
1168 | Power Transmission (Pallatana-Silchar-Bongariagaon) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Assam | Assam Electricity Grid Corporation Limited | Completed | 200.00 | 28-Sep-2012 | 18-10-2016 |
1169 | Power Transmission (Sibsagar) Project - RGGVY | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Assam | Assam Power Distribution Company Limited | Completed | 59.85 | 09-Feb-2009 | 18-10-2016 |
1170 | Power Transmission (Sonitpur) Project - RGGVY | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Assam | Assam Power Distribution Company Limited | Completed | 130.08 | 04-Feb-2009 | 18-10-2016 |