List of Infrastructure Projects – State Wise
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
- Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
- Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
- Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
No. of Projects in this Report: | 9243 | Total Project Cost(in Rs Crore): | 6,813,036.84 |
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
241 | Four laning of Wadpale-Bhogaon Khurd section in length of 39.6 km of NH-17* | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Maharashtra | Ministry of Road Transport and Highways | Pre-construction Stage | 817.10 | 30-Mar-2017 | 25-10-2019 |
242 | Four laning of Nalagampalli to AP/ Karnataka Border section in length of 47.7 km under NHDP-IV | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Andhra Pradesh | National Highways Authority of India (NHAI) | Pre-construction Stage | 503.10 | 30-Mar-2017 | 21-04-2017 |
243 | Four laning of Singhara-Bhinjhabal Section of NH6 from KM 310.806 to KM 414.982 under NHDP IV | Government Infrastructure Projects (PPP) | Transport | Roads and bridges | Odisha | National Highways Authority of India (NHAI) | Operation and Maintenance Stage | 1,288.07 | 29-Mar-2017 | 09-11-2019 |
244 | Implementation of 9.5 MLD Siddhghat/Sakri-Morchaghat multi village rural water supply scheme * | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Water supply pipeline | Madhya Pradesh | Madhya Pradesh Jal Nigam Maryadit | Under Construction | 89.27 | 28-Mar-2017 | 25-11-2019 |
245 | Implementation of rural electrification works in Murshidabad under Integrated Power Development Scheme* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Distribution Company Limited | Under Construction | 174.10 | 28-Mar-2017 | 22-11-2019 |
246 | Four laning of Jhansi-Khajuraho section in length of 85.4 km Package-II | Government Infrastructure Projects (PPP) | Transport | Roads and bridges | Multi State/ Centre | National Highways Authority of India (NHAI) | Operation and Maintenance Stage | 1,184.71 | 28-Mar-2017 | 09-11-2019 |
247 | Four laning of Waranga-Mahagaon section in length of 66.9 km | Government Infrastructure Projects (PPP) | Transport | Roads and bridges | Maharashtra | National Highways Authority of India (NHAI) | Operation and Maintenance Stage | 1,059.73 | 28-Mar-2017 | 09-11-2019 |
248 | Two laning with paved shoulders of Jhansi-Khajuraho section of NH 75 in UP and MP | Government Infrastructure Projects (PPP) | Transport | Roads and bridges | Multi State/ Centre | National Highways Authority of India (NHAI) | Operation and Maintenance Stage | 1,373.28 | 28-Mar-2017 | 09-11-2019 |
249 | Construction of two lane road over bridge in length of 1 km on NH-74 at Doiwala* | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Uttarakhand | Public Works Department, Uttarakhand | Pre-construction Stage | 69.50 | 28-Mar-2017 | 25-10-2019 |
250 | Upgradation of existing two lane road between Fata to Sitapur in length of 10.7 km on NH-109 | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Uttarakhand | Public Works Department, Uttarakhand | Under Construction | 95.57 | 28-Mar-2017 | 25-10-2019 |
251 | Implementation of sewerage scheme in Vidisha | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Sewage collection, treatment and disposal system | Madhya Pradesh | Municipal Council, Vidisha | Under Construction | 101.46 | 28-Mar-2017 | 08-11-2017 |
252 | Construction of road over bridge in length of 1.3 km at Khejuria* | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | West Bengal | West Bengal Highway Development Corporation Limited | Under Construction | 65.58 | 27-Mar-2017 | 27-11-2019 |
253 | Construction of four lane bridge across Varsova creek in length of 2.3 km | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Multi State/ Centre | National Highways Authority of India (NHAI) | Pre-construction Stage | 157.64 | 27-Mar-2017 | 07-10-2019 |
254 | Two laning of Dehri-Banjari-Akbarpur road (existing NH-2C) in lenght of 40.0 km* | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Bihar | Road Construction Department, Bihar | Under Construction | 172.05 | 25-Mar-2017 | 03-12-2019 |
255 | Upgradation of Pithoragarh-Tanakpur road in length of 27.6 km at Haldwani* | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Uttarakhand | Public Works Department, Uttarakhand | Pre-construction Stage | 232.81 | 25-Mar-2017 | 25-10-2019 |
256 | Implementation of 5.5 MLD Atru-Shergarh water supply scheme in Baran* | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Water supply pipeline | Rajasthan | Public Health Engineering Department, Rajasthan | Under Construction | 58.80 | 24-Mar-2017 | 05-11-2019 |
257 | Renovation of Kolaghat coal based power unit with a capacity of 630 MW - Stage I* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | West Bengal | West Bengal Power Development Corporation Limited | Under Construction | 5,040.00 | 23-Mar-2017 | 21-11-2019 |
258 | 8/6 Laning of Delhi Meerut Expressway from Km. 8.36- Km. 27.74 (UP Border to Dasna) oh NH-24 on HAM(Package II)* | Government Infrastructure Projects (PPP) | Transport | Roads and bridges | Uttar Pradesh | Ministry of Road Transport and Highways | Under Construction | 1,989.00 | 23-Mar-2017 | 09-11-2019 |
259 | Four/six laning of Bodare-Dhule section in length of 62.8 km under NHDP-IV | Government Infrastructure Projects (PPP) | Transport | Roads and bridges | Andhra Pradesh | National Highways Authority of India (NHAI) | Operation and Maintenance Stage | 1,315.00 | 23-Mar-2017 | 09-11-2019 |
260 | Implementation of rural electrification work in Pune & Amravati under DDUGJY scheme | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Maharashtra | Maharashtra State Electricity Distribution Company Limited | Completed | 60.74 | 23-Mar-2017 | 25-10-2019 |
261 | Laying of 320 kV Raigarh-Pugalur-Madakathara transmission line - Scheme 3 | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Multi State/ Centre | Power Grid Corporation of India Limited | Under Construction | 3,769.00 | 22-Mar-2017 | 25-10-2019 |
262 | Setting up of 10 MW solar photovoltaic power unit at Bandel, Kolaghat & Bakreswar * | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | West Bengal | West Bengal Power Development Corporation Limited | Under Construction | 70.00 | 21-Mar-2017 | 25-11-2019 |
263 | Implementation of rural electrification works in Amravati under IPDS scheme Phase-B (Part II)* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Maharashtra | Maharashtra State Electricity Distribution Company Limited | Pre-construction Stage | 80.66 | 21-Mar-2017 | 25-10-2019 |
264 | Implementation of rural electrification works in Kolhapur under IPDS scheme Phase-B (Part II)* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Maharashtra | Maharashtra State Electricity Distribution Company Limited | Pre-construction Stage | 51.07 | 21-Mar-2017 | 25-10-2019 |
265 | Implementation of rural electrification works in Nagpur Urban under IPDS scheme Phase-B (Part II)* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Maharashtra | Maharashtra State Electricity Distribution Company Limited | Pre-construction Stage | 103.16 | 21-Mar-2017 | 25-10-2019 |
266 | Upgradation of Beonabad-Ferargunj section in length of 26 km | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Andaman & Nicobar Islands (UT) | National Highways and Infrastructure Development Corporation Limited | Under Construction | 170.00 | 21-Mar-2017 | 25-10-2019 |
267 | Construction of bus terminal on 2.8 acres of land in Rajkot | Government Infrastructure Projects (PPP) | Transport | Urban public transport (except rolling stock) | Gujarat | Gujarat State Road Transport Corporation | Pre-construction Stage | 128.01 | 21-Mar-2017 | 01-10-2019 |
268 | Construction of bus terminal on 3.1 acres of land in Bhuj | Government Infrastructure Projects (PPP) | Transport | Urban public transport (except rolling stock) | Gujarat | Gujarat State Road Transport Corporation | Pre-construction Stage | 28.85 | 21-Mar-2017 | 01-10-2019 |
269 | Construction of bus terminal on 4.2 acres of land in Amreli | Government Infrastructure Projects (PPP) | Transport | Urban public transport (except rolling stock) | Gujarat | Gujarat State Road Transport Corporation | Pre-construction Stage | 40.43 | 21-Mar-2017 | 01-10-2019 |
270 | Construction of bus terminal on 5 acres of land at Nadiad | Government Infrastructure Projects (PPP) | Transport | Urban public transport (except rolling stock) | Gujarat | Gujarat State Road Transport Corporation | Pre-construction Stage | 50.71 | 21-Mar-2017 | 01-10-2019 |