This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
- Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
- Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
- Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
No. of Projects in this Report: | 9243 | Total Project Cost(in Rs Crore): | 6,813,036.84 |
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
991 | Setting up of 120 MW wind based power unit at Kalyandurg in Anantapur district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Hero Future Energies Limited | Under Construction | 600.00 | 08-Aug-2016 | 25-10-2019 |
992 | Two laning of Jath - Jamboti - Road section from km 25.000 to km 101.000 of SH-31 under DBFOT | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Karnataka | Karnataka Road Development Corporation Limited (KRDCL) | Under Construction | 322.35 | 08-Aug-2016 | 16-08-2019 |
993 | Wind Power (Bableshwar) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Karnataka | Hero Future Energies Limited | Under Construction | 250.00 | 08-Aug-2016 | 03-10-2016 |
994 | Upgradation of various roads in length of 69.5 Km at Madhugiri division in Tumkur district* | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Karnataka | Public Works, Ports and Inland Water Transport Department, Karnataka | Under Construction | 61.29 | 05-Aug-2016 | 26-11-2019 |
995 | Renovation of 360 MW Balimela Hydro Electric Power Project in Malkangiri district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Odisha | Odisha Hydro Power Corporation Limited | Under Construction | 382.91 | 05-Aug-2016 | 25-11-2019 |
996 | Development of a liquid terminal with a capacity of 1,00,000 KL at Kandla port in Kachchh district* | Government Infrastructure Projects (Traditional Procurement) | Transport | Ports (excluding captive) | Gujarat | Aegis Logistics Limited | Under Construction | 75.00 | 05-Aug-2016 | 25-10-2019 |
997 | Setting up of 11.2 MW solar photovoltaic based power unit at New Mangalore Port in Dakshina Kannada* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Karnataka | New Mangalore Port Trust | Under Construction | 112.00 | 04-Aug-2016 | 21-11-2019 |
998 | Setting up of 226.8 MW wind power unit at Amidala in Anantapur district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Skeiron Renewable Energy Amidyala Limited | Under Construction | 1,820.00 | 04-Aug-2016 | 25-10-2019 |
999 | Upgradation of Lohardaga-Gangupara-Peshrar road in length of 27.6 Km in Ranchi district | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Jharkhand | Department of Road Construction, Jharkhand | Completed | 74.72 | 04-Aug-2016 | 16-08-2019 |
1000 | Upgradation of NH-13 in length of 8.2 Km in Chitradurga district* | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Karnataka | Public Works, Ports and Inland Water Transport Department, Karnataka | Under Construction | 76.00 | 03-Aug-2016 | 26-11-2019 |
1001 | Substations (Bhadla & Bikaner) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Rajasthan | Power Grid Corporation of India Limited | Under Construction | 156.78 | 03-Aug-2016 | 25-10-2019 |
1002 | Transmission Line (Bhadla) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Rajasthan | Power Grid Corporation of India Limited | Under Construction | 193.58 | 03-Aug-2016 | 25-10-2019 |
1003 | Coal Based Power (Ghatampur) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Uttar Pradesh | Neyveli Uttar Pradesh Power Limited | Under Construction | 17,237.80 | 03-Aug-2016 | 22-12-2017 |
1004 | Road Upgradation (Lalganj-Haliya-Andawa-Manigaraha-MP Border) Project* | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Uttar Pradesh | Public Works Department, Uttar Pradesh | Under Construction | 93.75 | 01-Aug-2016 | 26-11-2019 |
1005 | Replacement of old crude oil pipeline between Chennai Port and Manali Refinery in length of 16.7 km in Chennai* | Government Infrastructure Projects (Traditional Procurement) | Energy | Oil pipelines | Tamil Nadu | Chennai Petroleum Corporation Limited | Under Construction | 258.00 | 01-Aug-2016 | 25-11-2019 |
1006 | Setting up of 15 MW Solar Power unit at Orai in Jalaun district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttar Pradesh | Shree Radhey Power & Ispat Private Limited | Under Construction | 150.00 | 01-Aug-2016 | 21-11-2019 |
1007 | Four-laning of a section under NHDP-IV, between Hubli - Hospet section of NH 63 on BOT (Toll) basis. | Government Infrastructure Projects (PPP) | Transport | Roads and bridges | Karnataka | Ministry of Road Transport and Highways | Operation and Maintenance Stage | 2,119.00 | 01-Aug-2016 | 09-11-2019 |
1008 | Doubling of Surendranagar-Rajkot railway line in length of 116.2 km | Government Infrastructure Projects (Traditional Procurement) | Transport | Railway track, tunnel, viaducts, bridges | Gujarat | Western Railway | Pre-construction Stage | 1,002.39 | 01-Aug-2016 | 25-10-2019 |
1009 | Food Park (Dehri)* | Government Infrastructure Projects (Traditional Procurement) | Social and Commercial Infrastructure | Common infrastructure for industrial parks, SEZ | Bihar | JVL Mega Food Park Private Limited | Under Construction | 150.00 | 01-Aug-2016 | 25-10-2019 |
1010 | Storm Water Drainage Scheme (Vijayawada) | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Storm water drainage system | Andhra Pradesh | Public Health and Municipal Engineering Department, Andhra Pradesh | Under Construction | 345.18 | 01-Aug-2016 | 25-10-2019 |
1011 | Water Supply Scheme (Tumkuru)* | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Water supply pipeline | Karnataka | Karnataka Urban Water Supply and Drainage Board | Pre-construction Stage | 127.51 | 01-Aug-2016 | 25-10-2019 |
1012 | Development of mega food park on 55 acres at Rihana Jattan in Kapurthala | Government Infrastructure Projects (Traditional Procurement) | Social and Commercial Infrastructure | Common infrastructure for industrial parks, SEZ | Punjab | Sukhjit Starch & Chemicals Limited | Under Construction | 128.28 | 01-Aug-2016 | 20-03-2017 |
1013 | Four laning of Loutolim road in length of 3.8 km | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Goa | Public Works Department, Goa | Under Construction | 184.05 | 31-Jul-2016 | 04-12-2019 |
1014 | Construction of mega food park on 79 acres at Kozhippara in Palakkad | Government Infrastructure Projects (Traditional Procurement) | Social and Commercial Infrastructure | Common infrastructure for industrial parks, SEZ | Kerala | Kerala Industrial Infrastructure Development Corporation Limited | Completed | 121.92 | 31-Jul-2016 | 29-11-2019 |
1015 | Road Upgradation (Khamaarpani-Sabarni-Lodhikheda-Reymond Chowk) Project* | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Madhya Pradesh | Public Works Department, Madhya Pradesh | Under Construction | 50.00 | 31-Jul-2016 | 26-11-2019 |
1016 | Upgradation of Lucknow-Ballia road in length of 43 km in Lucknow district* | Government Infrastructure Projects (Traditional Procurement) | Transport | Roads and bridges | Uttar Pradesh | Public Works Department, Uttar Pradesh | Under Construction | 114.53 | 31-Jul-2016 | 26-11-2019 |
1017 | Setting up of 10 MW solar based power unit at Alair in Nalgonda district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Telangana | Sri Ramcharan Power Projects | Under Construction | 100.00 | 31-Jul-2016 | 21-11-2019 |
1018 | Road Upgradation (Kodinar-Veraval) Project | Government Infrastructure Projects (PPP) | Transport | Roads and bridges | Gujarat | National Highways Authority of India (NHAI) | Operation and Maintenance Stage | 829.97 | 31-Jul-2016 | 11-11-2019 |
1019 | Katri Reservoir Scheme - Renovation* | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Irrigation (dams, channels, embankments, etc.) | Jharkhand | Water Resources Department, Jharkhand | Pre-construction Stage | 91.39 | 31-Jul-2016 | 25-10-2019 |
1020 | Laying of 190 CKM NLC-Karaikal 230 kV D/C line in Puducherry | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Puducherry (UT) | Power Grid Corporation of India Limited | Completed | 102.79 | 31-Jul-2016 | 25-10-2019 |