This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9242 Total Project Cost(in Rs Crore): 6,813,008.32
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
301 Aarohi Solar Pvt. Ltd, Hindupur (50 MW) Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Andhra Pradesh Operation and Maintenance Stage 411.86 Not Available 26-11-2018
302 ACME Jaisalmer Solar Power Pvt. Ltd Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Andhra Pradesh Operation and Maintenance Stage 177.35 Not Available 22-11-2018
303 Dayanidhi Solar Power Pvt. Ltd, Shantipuram Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Andhra Pradesh Operation and Maintenance Stage 326.60 Not Available 22-11-2018
304 MEIL Green Power (Anantpur) Limited 50MW CSP Government Infrastructure Projects (PPP) Energy Electricity generation (grid) Andhra Pradesh Operation and Maintenance Stage 848.00 Not Available 22-11-2018
305 Niranjana Solar Energy Pvt. Ltd., Pathikonda (20 MW) Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Andhra Pradesh Operation and Maintenance Stage 164.00 Not Available 22-11-2018
306 Vishwatma Solar Energy Pvt Ltd. Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Andhra Pradesh Operation and Maintenance Stage 245.60 Not Available 22-11-2018
307 East Coast Energy Private Limited (ECEPL) - Coal based Thermal Power Plant near Kakarapalli Village Government Infrastructure Projects (PPP) Energy Electricity generation (grid) Andhra Pradesh Operation and Maintenance Stage 9,343.15 Not Available 20-11-2018
308 Gautami Combined Cycle Power Plant Government Infrastructure Projects (PPP) Energy Electricity generation (grid) Andhra Pradesh Operation and Maintenance Stage 1,800.00 Not Available 20-11-2018
309 GMR Rajahmundry Energy Ltd - Gas based combined cycle power project Government Infrastructure Projects (PPP) Energy Electricity generation (grid) Andhra Pradesh Operation and Maintenance Stage 4,940.00 Not Available 20-11-2018
310 Krishnapatnam Thermal Power Project Government Infrastructure Projects (PPP) Energy Electricity generation (grid) Andhra Pradesh Operation and Maintenance Stage 2,678.40 Not Available 20-11-2018
311 Design Construction Finance Operation and Maintenance of Four Laning of Kadapa Renigunta Road under PPP Government Infrastructure Projects (PPP) Transport Roads and bridges Andhra Pradesh Andhra Pradesh Road Development Corporation Operation and Maintenance Stage 609.00 Not Available 23-03-2018
312 Road (Maharashtra/AP Border-Islam Nagar NH-7) Project Government Infrastructure Projects (PPP) Transport Roads and bridges Andhra Pradesh National Highways Authority of India (NHAI) Operation and Maintenance Stage 360.00 05-May-2007 20-03-2018
313 Construction of four lane connecting road at Vishakhapatnam Port Government Infrastructure Projects (PPP) Transport Roads and bridges Andhra Pradesh National Highways Authority of India (NHAI) Operation and Maintenance Stage 93.79 Not Available 06-12-2017
314 Construction of bus rapid transport system in 15.5 km at Vijayawada in Krishna Government Infrastructure Projects (Traditional Procurement) Transport Urban public transport (except rolling stock) Andhra Pradesh Vijayawada Municipal Corporation Completed 152.64 31-Dec-2007 05-12-2017
315 Implementation of 1600 MW Krishnapatnam coal based power unit in Nellore Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Andhra Pradesh Andhra Pradesh Power Development Company Limited Completed 8,340.00 05-Mar-2012 05-12-2017
316 Stregthening and Widening of Dharmavaram - Rajahmundry road Government Infrastructure Projects (PPP) Transport Roads and bridges Andhra Pradesh National Highways Authority of India (NHAI) Operation and Maintenance Stage 219.00 30-Oct-2001 20-09-2017
317 Road Upgradation (Kadapa-Pulivendula) KP-04 Project Government Infrastructure Projects (PPP) Transport Roads and bridges Andhra Pradesh Andhra Pradesh Road Development Corporation Operation and Maintenance Stage 71.72 25-Jan-2010 17-09-2017
318 Road Upgradation (Pulivendula-Parnapalli) Government Infrastructure Projects (PPP) Transport Roads and bridges Andhra Pradesh Andhra Pradesh Road Development Corporation Operation and Maintenance Stage 23.94 19-Feb-2009 17-09-2017
319 Bridge across Krishna river Government Infrastructure Projects (PPP) Transport Roads and bridges Andhra Pradesh Andhra Pradesh Road Development Corporation Operation and Maintenance Stage 71.00 06-Oct-2003 25-08-2017
320 Road Upgradation (Kadapa-Pulivendula) KP-02 Project Government Infrastructure Projects (PPP) Transport Roads and bridges Andhra Pradesh Andhra Pradesh Road Development Corporation Operation and Maintenance Stage 51.95 09-Oct-2009 25-08-2017
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.