List of Infrastructure Projects – State Wise List of Infrastructure Projects – State Wise

This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9242 Total Project Cost(in Rs Crore): 6,813,008.32
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
521 Water Supply Scheme (Thiruvottiyur Municipality) Government Infrastructure Projects (Traditional Procurement) Water Sanitation Water supply pipeline Tamil Nadu Chennai Metropolitan Water Supply and Sewerage Board (CMWSSB) Completed 85.12 06-May-2010 04-12-2019
522 Water Supply Scheme (Urvakonda, Kudair, Vajrakarur & Vidapankal) Government Infrastructure Projects (Traditional Procurement) Water Sanitation Water supply pipeline Andhra Pradesh Rural Water Supply and Sanitation Department, Andhra Pradesh Under Construction 56.00 09-Nov-2013 04-12-2019
523 Water Supply Scheme in NIT Area*# Government Infrastructure Projects (Traditional Procurement) Water Sanitation Water supply pipeline Maharashtra Nagpur Municipal Corporation Under Construction 141.07 Not Available 04-12-2019
524 Wind Based Power (Davangere) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka Bharat Electronics Limited Completed 0.00 23-Nov-2012 04-12-2019
525 Wind Power (Bhanwad) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Gujarat Mineral Development Corporation Limited Completed 305.32 30-Jun-2012 04-12-2019
526 Wind Power (Jaora) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh PTC India Limited Completed 150.00 28-Jan-2016 04-12-2019
527 24x7 Water Supply (Basavakalyan) Project* Government Infrastructure Projects (Traditional Procurement) Water Sanitation Water supply pipeline Karnataka Karnataka Urban Infrastructure Development and Finance Corporation Under Construction 87.82 30-Jan-2015 03-12-2019
528 24x7 Water Supply (Bidar) Project* Government Infrastructure Projects (Traditional Procurement) Water Sanitation Water supply pipeline Karnataka Karnataka Urban Infrastructure Development and Finance Corporation Under Construction 69.77 30-Jan-2015 03-12-2019
529 Ajay Barrage Project Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Jharkhand Water Resources Department, Jharkhand Completed 351.85 13-Aug-1982 03-12-2019
530 Amhata Small Hydel Power Project* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh New and Renewable Energy Department, Madhya Pradesh Under Construction 107.20 01-Mar-2014 03-12-2019
531 Angul Aluminium Park* Government Infrastructure Projects (Traditional Procurement) Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Odisha Odisha Industrial Infrastructure Development Corporation Under Construction 130.00 23-Aug-2015 03-12-2019
532 Arunavati Major Irrigation Project#* Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Maharashtra Vidarbha Irrigation Development Corporation Under Construction 331.18 06-Dec-1978 03-12-2019
533 AVR Handri Niva Sujala Shravanthi Project - Phase I Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Andhra Pradesh Water Resources Department, Andhra Pradesh Completed 1,571.71 25-Feb-2005 03-12-2019
534 AVR Handri Niva Sujala Shravanthi Project - Phase II Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Andhra Pradesh Water Resources Department, Andhra Pradesh Completed 3,440.21 04-Dec-2006 03-12-2019
535 Barapullah Elevated Corridor Project [Phase-III] Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges Delhi (UT) Public Works Department, Delhi Completed 1,260.63 31-Mar-2015 03-12-2019
536 Barnar Irrigation Scheme (Sono Causeway) Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Bihar Water Resources Department, Bihar Completed 590.98 Not Available 03-12-2019
537 Bawanthadi Irrigation Project Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Maharashtra Vidarbha Irrigation Development Corporation Completed 813.85 Not Available 03-12-2019
538 Bhadra Reservoir Project-Modernization Government Infrastructure Projects (Traditional Procurement) Water Sanitation Irrigation (dams, channels, embankments, etc.) Karnataka Karnataka Neeravari Nigam Limited Completed 1,324.00 31-Dec-2007 03-12-2019
539 Bhakra Left Bank Power Project - Expansion Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Punjab Bhakra Beas Management Board Completed 490.00 Not Available 03-12-2019
540 Bridge (Chennai-Trichy-Dindigul Road) Project Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges Tamil Nadu Public Works Department, Tamil Nadu Completed 62.53 06-Nov-2013 03-12-2019
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.