This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 20 August 2019
No. of Projects in this Report: 9407 Total Project Cost(in Rs Crore): 6,776,440.49
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
381 Setting up of 20 MW Roura-II hydel power unit in Kinnaur district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Under Construction 159.20 14-Aug-2019 14-08-2019
382 Setting up of 24 MW Baragaon hydel power unit in Kullu district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Operation and Maintenance Stage 174.81 14-Aug-2019 14-08-2019
383 Setting up of 24 MW Kut hydel power unit in Shimla district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Under Construction 189.50 14-Aug-2019 14-08-2019
384 Setting up of 24.6 MW Wanger-Homte hydel power unit in Kinnaur district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Under Construction 274.50 14-Aug-2019 14-08-2019
385 Setting up of 25 MW Lambadug hydel power unit in Kangra district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Under Construction 149.81 14-Aug-2019 14-08-2019
386 Setting up of 6 MW Baner hydel power unit in Kangra district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Operation and Maintenance Stage 54.59 14-Aug-2019 14-08-2019
387 Setting up of 9 MW Rala hydel power unit in Kinnaur district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Under Construction 58.04 14-Aug-2019 14-08-2019
388 Setting up of 9.6 MW Jeori hydel power unit in Shimla district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Under Construction 74.16 14-Aug-2019 14-08-2019
389 Two laning of Jhalawar-Ujjain section in length of 31.0 Km Government Infrastructure Projects (PPP) Transport Roads and bridges Rajasthan Public Works Department, Rajasthan Operation and Maintenance Stage 75.88 14-Aug-2019 14-08-2019
390 Two laning of Khushkhera-Kasola Chowk in length of 8.5 Km Government Infrastructure Projects (PPP) Transport Roads and bridges Rajasthan Public Works Department, Rajasthan Operation and Maintenance Stage 34.50 14-Aug-2019 14-08-2019
391 Yamuna Expressway Connecting Greater Noida to Agra Government Infrastructure Projects (PPP) Transport Roads and bridges Uttar Pradesh Yamuna Expressway Industrial Development Authority (YEA) Operation and Maintenance Stage 14,000.00 14-Aug-2019 14-08-2019
392 Baspa Hydel Power Project - Stage II Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Operation and Maintenance Stage 1,629.84 13-Aug-2019 13-08-2019
393 Bhina-Khimalsa-Malthon Road Project Government Infrastructure Projects (PPP) Transport Roads and bridges Madhya Pradesh Madhya Pradesh Road Development Corporation Limited (MPRDC) Operation and Maintenance Stage 67.30 13-Aug-2019 13-08-2019
394 Dhamara Port Road Government Infrastructure Projects (PPP) Transport Ports (excluding captive) Odisha Department of Commerce and Transport, Odisha Operation and Maintenance Stage 10,016.00 13-Aug-2019 13-08-2019
395 Establishment of Container Terminal and O & M of handling equipment at multipurpose berth, Visakhapatnam Port Government Infrastructure Projects (PPP) Transport Ports (excluding captive) Andhra Pradesh Visakhapatnam Port Trust Operation and Maintenance Stage 108.00 13-Aug-2019 13-08-2019
396 Manawar-Singhan-Kukshi Government Infrastructure Projects (PPP) Transport Roads and bridges Madhya Pradesh Madhya Pradesh Road Development Corporation Limited (MPRDC) Operation and Maintenance Stage 96.73 13-Aug-2019 13-08-2019
397 Mechanisation of coal handling facilities & upgradation of general cargo berth at outer harbour,Visakhapatnam port Government Infrastructure Projects (PPP) Transport Ports (excluding captive) Andhra Pradesh Visakhapatnam Port Trust Operation and Maintenance Stage 640.40 13-Aug-2019 13-08-2019
398 Road Upgradation Project (Biaora- Rajasthan) Project Government Infrastructure Projects (PPP) Transport Roads and bridges Madhya Pradesh Madhya Pradesh Road Development Corporation Limited (MPRDC) Operation and Maintenance Stage 221.00 13-Aug-2019 13-08-2019
399 Setting up of 100 MW Malana II hydel power unit in Kullu district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Operation and Maintenance Stage 981.91 13-Aug-2019 13-08-2019
400 Setting up of 1000 MW Karchham Wangtoo hydel power unit in Kinnaur district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Operation and Maintenance Stage 6,900.00 13-Aug-2019 13-08-2019
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis.