List of Infrastructure Projects – State Wise List of Infrastructure Projects – State Wise

This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 16 August 2019
No. of Projects in this Report: 9412 Total Project Cost(in Rs Crore): 6,776,714.14
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
221 Rehabilitation and upgrading of Forbesganj - Jogbani road Government Infrastructure Projects (PPP) Transport Roads and bridges Bihar National Highways Authority of India (NHAI) Under Construction 322.00 14-Aug-2019 14-08-2019
222 Road Upgradation (Vadodara-Bharuch NH-8) Project Government Infrastructure Projects (PPP) Transport Roads and bridges Gujarat National Highways Authority of India (NHAI) Operation and Maintenance Stage 1,450.00 14-Aug-2019 14-08-2019
223 Setting up of 12 MW Upper Joiner hydel power unit in Chamba district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Operation and Maintenance Stage 72.25 14-Aug-2019 14-08-2019
224 Setting up of 13 MW Lower Uhl hydel power unit in Mandi district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Under Construction 102.62 14-Aug-2019 14-08-2019
225 Setting up of 13.5 MW Upper Nanti hydel power unit in Shimla Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Under Construction 80.66 14-Aug-2019 14-08-2019
226 Setting up of 14 MW nanti hydel power unit in Shimla district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Operation and Maintenance Stage 66.94 14-Aug-2019 14-08-2019
227 Setting up of 150 MW Sorang hydel power unit in Kinnaur district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Under Construction 586.00 14-Aug-2019 14-08-2019
228 Setting up of 16 MW Patikari hydel power unit in Mandi district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Operation and Maintenance Stage 115.63 14-Aug-2019 14-08-2019
229 Setting up of 180 MW Bajoli Holi hydel power unit in Chamba district. Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Under Construction 1,681.82 14-Aug-2019 14-08-2019
230 Setting up of 192 MW Allain Duhangan hydel power unit in Kullu district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Operation and Maintenance Stage 206.56 14-Aug-2019 14-08-2019
231 Setting up of 20 MW Roura-II hydel power unit in Kinnaur district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Under Construction 159.20 14-Aug-2019 14-08-2019
232 Setting up of 24 MW Baragaon hydel power unit in Kullu district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Operation and Maintenance Stage 174.81 14-Aug-2019 14-08-2019
233 Setting up of 24 MW Kut hydel power unit in Shimla district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Under Construction 189.50 14-Aug-2019 14-08-2019
234 Setting up of 24.6 MW Wanger-Homte hydel power unit in Kinnaur district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Under Construction 274.50 14-Aug-2019 14-08-2019
235 Setting up of 25 MW Lambadug hydel power unit in Kangra district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Under Construction 149.81 14-Aug-2019 14-08-2019
236 Setting up of 6 MW Baner hydel power unit in Kangra district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Operation and Maintenance Stage 54.59 14-Aug-2019 14-08-2019
237 Setting up of 9 MW Rala hydel power unit in Kinnaur district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Under Construction 58.04 14-Aug-2019 14-08-2019
238 Setting up of 9.6 MW Jeori hydel power unit in Shimla district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Himachal Pradesh Directorate of Energy, Himachal Pradesh Under Construction 74.16 14-Aug-2019 14-08-2019
239 Two laning of Jhalawar-Ujjain section in length of 31.0 Km Government Infrastructure Projects (PPP) Transport Roads and bridges Rajasthan Public Works Department, Rajasthan Operation and Maintenance Stage 75.88 14-Aug-2019 14-08-2019
240 Two laning of Khushkhera-Kasola Chowk in length of 8.5 Km Government Infrastructure Projects (PPP) Transport Roads and bridges Rajasthan Public Works Department, Rajasthan Operation and Maintenance Stage 34.50 14-Aug-2019 14-08-2019