List of Infrastructure Projects – State Wise
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
- Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
- Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
- Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
No. of Projects in this Report: | 9243 | Total Project Cost(in Rs Crore): | 6,813,036.84 |
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
201 | Implementation of rural electrification works at Khamgaon, Buldhana & Malkapur - Infra Plan II - Phase A | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Maharashtra | Maharashtra State Electricity Distribution Company Limited | Under Construction | 102.61 | 06-Sep-2014 | 04-12-2019 |
202 | Implementation of rural electrification works at Manchar - Infra Plan II - Phase A | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Maharashtra | Maharashtra State Electricity Distribution Company Limited | Completed | 73.50 | 31-Oct-2013 | 04-12-2019 |
203 | Implementation of rural electrification works at Nerul Urban- Infra Plan II - Phase C* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Maharashtra | Maharashtra State Electricity Distribution Company Limited | Under Construction | 61.96 | 30-Jun-2014 | 04-12-2019 |
204 | Implementation of rural electrification works at Panvel Urban - Infra Plan II - Phase C* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Maharashtra | Maharashtra State Electricity Distribution Company Limited | Under Construction | 153.97 | 30-Jun-2014 | 04-12-2019 |
205 | Implementation of rural electrification works at Raipur city-I and II under IPDS | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Chhattisgarh | Chhattisgarh State Power Distribution Company Limited | Completed | 75.54 | 08-Mar-2017 | 04-12-2019 |
206 | Implementation of rural electrification works at Saswad - Infra Plan II - Phase A | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Maharashtra | Maharashtra State Electricity Distribution Company Limited | Completed | 59.51 | 31-Oct-2013 | 04-12-2019 |
207 | Implementation of rural electrification works at Vashi Urban - Infra Plan II - Phase C* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Maharashtra | Maharashtra State Electricity Distribution Company Limited | Under Construction | 119.37 | 30-Jun-2014 | 04-12-2019 |
208 | Implementation of rural electrification works in Bilaspur under IPDS | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Chhattisgarh | Chhattisgarh State Power Distribution Company Limited | Completed | 105.14 | 08-Mar-2017 | 04-12-2019 |
209 | Implementation of rural electrification works in Dehradun under DDUGJY | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Uttarakhand | Uttarakhand Power Corporation Limited | Completed | 71.05 | 11-Aug-2017 | 04-12-2019 |
210 | Implementation of rural electrification works in Garhwal under DDUGJY | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Uttarakhand | Uttarakhand Power Corporation Limited | Completed | 51.32 | 11-Aug-2017 | 04-12-2019 |
211 | Implementation of rural electrification works in Haridwar under DDUGJY | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Uttarakhand | Uttarakhand Power Corporation Limited | Completed | 124.78 | 11-Aug-2017 | 04-12-2019 |
212 | Implementation of rural electrification works in Nainital & Bageshwar under DDUGJY | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Uttarakhand | Uttarakhand Power Corporation Limited | Completed | 57.19 | 11-Aug-2017 | 04-12-2019 |
213 | Implementation of rural electrification works in Nashik under RAPDRP-Part B | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Maharashtra | Maharashtra State Electricity Distribution Company Limited | Completed | 85.68 | 21-Jan-2012 | 04-12-2019 |
214 | Implementation of rural electrification works in Udham Singh Nagar under DDUGJY | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Uttarakhand | Uttarakhand Power Corporation Limited | Completed | 149.12 | 11-Aug-2017 | 04-12-2019 |
215 | Implementation of sewage treatment plant of 15 MLD at Trombay in Mumbai | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Sewage collection, treatment and disposal system | Maharashtra | Rashtriya Chemicals and Fertilizers Limited | Under Construction | 200.00 | 31-Oct-2014 | 04-12-2019 |
216 | Implementation of sewerage scheme at C Block and G1 Block in Kerala#* | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Sewage collection, treatment and disposal system | Kerala | Local Self Government Department, Kerala | Under Construction | 64.86 | 11-Dec-2012 | 04-12-2019 |
217 | Implementation of sewerage scheme at E-2 and E-3 zone of Jodhpur | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Sewage collection, treatment and disposal system | Rajasthan | Jodhpur Development Authority | Completed | 54.81 | 07-Jul-2012 | 04-12-2019 |
218 | Implementation of Sewerage Scheme in Moradabad district | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Sewage collection, treatment and disposal system | Uttar Pradesh | Uttar Pradesh State Ganga River Conservation Agency | Completed | 279.91 | 21-Oct-2011 | 04-12-2019 |
219 | Implementation of Sonthi lift irrigation scheme on 39536.9 acres in Gulbarga & Yadgir | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Irrigation (dams, channels, embankments, etc.) | Karnataka | Krishna Bhagya Jala Nigam Limited | Under Construction | 600.00 | 11-Oct-2006 | 04-12-2019 |
220 | Implementation of water supply scheme at Karambakkam, Nolambur and Injambakkam in Chennai district | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Water supply pipeline | Tamil Nadu | Chennai Metropolitan Water Supply and Sewerage Board (CMWSSB) | Completed | 60.86 | 09-May-2013 | 04-12-2019 |