List of Infrastructure Projects – State Wise List of Infrastructure Projects – State Wise

This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9242 Total Project Cost(in Rs Crore): 6,813,008.32
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
141 Setting up of 50 MW solar power unit at Bhonigir in Nalgonda* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Telangana Acme Solar Power Technology Private Limited Under Construction 389.77 31-Aug-2016 21-11-2019
142 Setting up of 30 MW solar power unit at Mankhera in Mansa district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Punjab Acme Solar Rooftop Systems Private Limited Completed 229.90 08-May-2015 05-12-2016
143 15 MW Solar Based Power (Wadgam) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Acme Solar Technologies (Gujarat) Private Limited Completed 150.00 Not Available 08-12-2015
144 40 MW Solar PV Project in Andhra Pradesh ACME Tele* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Acme Tele Power Limited Under Construction 255.48 01-Oct-2014 05-11-2019
145 Solar Photovoltaic Power (Gaya) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Bihar Acme Tele Power Limited Completed 350.00 Not Available 20-04-2016
146 10 MW Solar PV Project in Karnataka - ACME Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka Acme Tele Power Limited Not Available 54.82 01-Nov-2013 27-09-2015
147 Solar Based Power (Khurda) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Odisha Acme Tele Power Limited Under Construction 200.00 Not Available 27-09-2015
148 Wind Power (Badnawar - 24MW) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh Acorn Properties Private Limited Under Construction 168.00 29-Oct-2014 26-02-2016
149 Setting up of 50 MW Wind Power Unit in Anantapur district* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Adani Enterprises Limited Pre-construction Stage 250.00 12-Apr-2016 01-11-2019
150 Setting up of 50.4 MW wind power unit at Rajgadh in Jaisalmer district* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Rajasthan Adani Green Energy (MP) Limited Under Construction 278.10 17-Aug-2016 21-11-2019
151 Solar Power (Ramanathapuram) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Tamil Nadu Adani Green Energy (Tamil Nadu) Limited Completed 4,536.00 15-Sep-2015 29-06-2016
152 Setting up of 50 MW solar power unit at Badanpur in Jhansi district* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Uttar Pradesh Adani Green Energy (UP) Limited Under Construction 335.70 30-May-2016 21-11-2019
153 Setting up of 20 MW solar power unit at Sayala in Parbhani district* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Maharashtra Adani Green Energy Limited Under Construction 140.00 16-Jun-2016 21-11-2019
154 Setting up of 100 MW solar power unit at Sardargarh and Chughe Kalan in Bhatinda district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Punjab Adani Green Energy Limited Completed 640.00 31-Jan-2015 28-11-2016
155 Tiroda Coal Based Power Project - Phase I & II Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Maharashtra Adani Power Maharashtra Limited Completed 9,263.00 Not Available 16-12-2015
156 Laying of 1000 Km long transmission line at Mundra in Kachchh district Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Gujarat Adani Power Private Limited Completed 1,380.00 31-May-2009 31-10-2016
157 40 MW Solar Power (Banaskantha) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Adani Power Private Limited Completed 700.00 30-Sep-2010 01-12-2015
158 1320 MW Coal Based Power (Kawai) Project Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Rajasthan Adani Power Rajasthan Limited Completed 5,889.00 20-Jan-2010 16-12-2015
159 Setting up of 20 MW solar power unit at Hubballi in Dharwad Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka Aditya Birla Nuvo Limited Under Construction 178.00 14-Dec-2016 13-03-2017
160 Setting up of 20 MW solar power unit at Mullenger in Bengaluru Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka Aditya Birla Nuvo Limited Under Construction 200.00 14-Dec-2016 13-03-2017
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.