List of Infrastructure Projects – State Wise
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
- Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
- Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
- Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
No. of Projects in this Report: | 9243 | Total Project Cost(in Rs Crore): | 6,813,036.84 |
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
361 | Solapur-Pakni DL Railway Line | Government Infrastructure Projects (Traditional Procurement) | Transport | Railway track, tunnel, viaducts, bridges | Maharashtra | Central Railway | Completed | 50.00 | 28-Nov-2005 | 27-09-2015 |
362 | Solar Based Power (Khurda) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Odisha | Acme Tele Power Limited | Under Construction | 200.00 | Not Available | 27-09-2015 |
363 | Solar Based Power (Ludiya) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | India Solar Ray Power Private Limited | Under Construction | 90.00 | Not Available | 27-09-2015 |
364 | Solar Park (Kurnool & Gani) | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Solar Energy Corporation of India | Completed | 0.00 | 02-Dec-2014 | 27-09-2015 |
365 | Solar Photovoltaic (T. Lingampalli) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Telangana | Emmvee Energy Private Limited | Completed | 60.00 | Not Available | 27-09-2015 |
366 | Solar Photovoltaic Power (Alot) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Madhya Pradesh | Hero Future Energies Limited | Completed | 227.50 | Not Available | 27-09-2015 |
367 | Solar Photovoltaic Power (Andaman & Nicobar) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andaman & Nicobar Islands (UT) | NTPC Limited | Completed | 52.09 | 12-Dec-2011 | 27-09-2015 |
368 | Solar Photovoltaic Power (Dadri) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttar Pradesh | NTPC Limited | Completed | 40.38 | 07-Mar-2012 | 27-09-2015 |
369 | Solar Photovoltaic Power (Kukshi) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Madhya Pradesh | Alfa Infraprop Private Limited | Completed | 200.00 | Not Available | 27-09-2015 |
370 | Solar Photovoltaic Power (Rajkot) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | Ganges Green Energy Private Limited | Completed | 250.00 | Not Available | 27-09-2015 |
371 | Solar Photovoltaic Power (Rewara) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Rajasthan | Viraj Renewable Energy Private Limited | Completed | 190.00 | Not Available | 27-09-2015 |
372 | Solar Photovoltaic Power (Surendranagar) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | Mi Mysolar24 Private Limited | Completed | 120.00 | Not Available | 27-09-2015 |
373 | Solar Power (Kolihal) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Karnataka | Madhav Solar (Karnataka) Private Limited | Completed | 50.00 | Not Available | 27-09-2015 |
374 | Solar Power (Kutch) Project - Phase 1 | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | Solar Semiconductor Power Company (India) Private Limited | Completed | 100.00 | Not Available | 27-09-2015 |
375 | Solar Power (Kutch) Project - Phase 2 | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | Solar Semiconductor Power Company (India) Private Limited | Completed | 100.00 | Not Available | 27-09-2015 |
376 | Solar Power (Munanjipatti) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Tamil Nadu | Brakes India Limited | Completed | 70.00 | Not Available | 27-09-2015 |
377 | Solar Power (Ragunathamadai) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Tamil Nadu | JVS Exports Limited | Completed | 50.00 | Not Available | 27-09-2015 |
378 | Solar Power (Sakri) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Maharashtra | Varroc Engineering Private Limited | Completed | 50.00 | Not Available | 27-09-2015 |
379 | Solar Power (Sambepalli) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Pashupathinath Power Projects Private Limited | Completed | 50.00 | Not Available | 27-09-2015 |
380 | Solar Power (Tiruchchirappalli) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Tamil Nadu | Chemtrols Solar Private Limited | Completed | 100.00 | Not Available | 27-09-2015 |