List of Infrastructure Projects – State Wise List of Infrastructure Projects – State Wise

This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9242 Total Project Cost(in Rs Crore): 6,813,008.32
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
721 Aircraft Maintenance Hangar (Kochi) Government Infrastructure Projects (PPP) Transport Airports Kerala Cochin International Airport Limited Operation and Maintenance Stage 42.00 Not Available 01-10-2019
722 Bus cum Truck Terminal at Alisha PS & District Burdwan Government Infrastructure Projects (PPP) Transport Urban public transport (except rolling stock) West Bengal Burdwan Development Authority Operation and Maintenance Stage 65.00 Not Available 01-10-2019
723 Bus cum Truck Terminal at Nababhat Government Infrastructure Projects (PPP) Transport Urban public transport (except rolling stock) West Bengal Burdwan Development Authority Operation and Maintenance Stage 35.00 Not Available 01-10-2019
724 Bus Rapid Transport System (Ahmedabad) Phase IA Government Infrastructure Projects (PPP) Transport Urban public transport (except rolling stock) Gujarat Gujarat Infrastructure Development Board Operation and Maintenance Stage 87.60 Not Available 01-10-2019
725 Development of a Container Terminal at Tuna Tekra in Kandla Port Kutch region in the State of Gujarat on DBFOT basis Government Infrastructure Projects (PPP) Transport Ports (excluding captive) Gujarat Ministry of Shipping Pre-construction Stage 5,991.71 Not Available 01-10-2019
726 Development of a multipurpose Berth and a Mechanised Berth at Haldia Dock -II (South), Haldia Dock Complex, Kolkata Port Trust Government Infrastructure Projects (PPP) Transport Ports (excluding captive) West Bengal Ministry of Shipping Operation and Maintenance Stage 886.10 Not Available 01-10-2019
727 Multilevel Parking at Sector 17 Government Infrastructure Projects (PPP) Transport Urban public transport (except rolling stock) Haryana Chandigarh Municipal Corporation Operation and Maintenance Stage 60.00 Not Available 01-10-2019
728 Jamb Wind Power Project, Satara district Government Infrastructure Projects (PPP) Energy Renewable energy (grid) Maharashtra Operation and Maintenance Stage 165.90 Not Available 19-09-2019
729 Airport (Kolkata) Project - Modernisation Government Infrastructure Projects (Traditional Procurement) Transport Airports West Bengal Airports Authority of India (AAI) Completed 2,500.00 Not Available 16-09-2019
730 Barhi-Hazaribagh NH-33 Road Project (NHDP - Phase III B) Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges Jharkhand National Highways Authority of India (NHAI) Completed 392.00 Not Available 16-09-2019
731 Four laning of Pune-Sholapur section of NH 9 under NHDP Phase III, length 110.05 km  Package II Government Infrastructure Projects (PPP) Transport Roads and bridges Maharashtra Ministry of Road Transport and Highways Operation and Maintenance Stage 1,110.00 Not Available 16-09-2019
732 Brackish Water Desalination Plant Government Infrastructure Projects (PPP) Water Sanitation Water treatment plants Rajasthan Rajasthan State Mines and Minerals Limited Operation and Maintenance Stage 300.00 Not Available 13-09-2019
733 Door to Dump waste disposal Central zone, Ahmedabad Government Infrastructure Projects (PPP) Water Sanitation Solid waste management Gujarat Ahmedabad Municipal Corporation Operation and Maintenance Stage 30.00 Not Available 13-09-2019
734 Door to Dump waste disposal North zone, Ahmedabad Government Infrastructure Projects (PPP) Water Sanitation Solid waste management Gujarat Ahmedabad Municipal Corporation Operation and Maintenance Stage 34.00 Not Available 13-09-2019
735 Dedicated Container Terminal at Pipavav Port Government Infrastructure Projects (PPP) Transport Ports (excluding captive) Gujarat Gujarat Maritime Board (GMB) Operation and Maintenance Stage 2,000.00 Not Available 21-08-2019
736 Solid Waste Management (Rajkot) Government Infrastructure Projects (PPP) Water Sanitation Solid waste management Gujarat Rajkot Municipal Corporation Operation and Maintenance Stage 8.67 Not Available 21-08-2019
737 Development of 93 km in Mumbai Urban Transport Project (MUTP) Phase I project Government Infrastructure Projects (Traditional Procurement) Transport Railway track, tunnel, viaducts, bridges Maharashtra Mumbai Railway Vikas Corporation Limited Completed 4,452.00 Not Available 19-08-2019
738 Maheshwaram Transmission Limited Government Infrastructure Projects (PPP) Energy Electricity transmission Telangana Operation and Maintenance Stage 345.00 Not Available 19-08-2019
739 Nangal Dam-Talwara BG Railway Line Government Infrastructure Projects (Traditional Procurement) Transport Railway track, tunnel, viaducts, bridges Multi State/ Centre Northern Railway Completed 2,100.00 Not Available 19-08-2019
740 Transmission Line associated with Farakka - III Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission West Bengal Power Grid Corporation of India Limited Completed 204.00 Not Available 19-08-2019
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.