List of Infrastructure Projects – State Wise List of Infrastructure Projects – State Wise

This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9243 Total Project Cost(in Rs Crore): 6,813,036.84
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
131 50 MW Solar PV Project in Telangana - ACME solar Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Telangana Acme Solar Energy Private Limited Completed 306.23 01-Dec-2014 20-11-2019
132 Setting up of 25 MW solar photovoltaic power unit at Khilchipur Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh Acme Solar Energy Private Limited Completed 150.00 Not Available 25-05-2017
133 Setting up of 30 MW solar photovoltaic power unit at Sikuan in Kalahandi district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Odisha Acme Solar Energy Private Limited Completed 210.00 30-Jun-2014 18-12-2016
134 30 MW Solar PV Project in Telangana Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Telangana Acme Solar Energy Private Limited Under Construction 186.76 01-Dec-2014 27-09-2015
135 Setting up of 50 MW solar power unit at Plot-P1 Galiveedu mandal in Kadappa district* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Acme Solar Holdings Private Limited Under Construction 422.00 16-Aug-2016 01-11-2019
136 Setting up of 50 MW solar power unit at Plot-P3 in Ananthapuramu Solar Park* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Acme Solar Holdings Private Limited Under Construction 389.00 16-Aug-2016 01-11-2019
137 Setting up of 50 MW solar power unit at Plot-P6 Galiveedu mandal in Kadappa district* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Andhra Pradesh Acme Solar Holdings Private Limited Under Construction 371.00 16-Aug-2016 01-11-2019
138 Setting up of 40 MW solar power unit at Ranna-Belagali in Bagalkot district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka Acme Solar Holdings Private Limited Under Construction 400.00 02-Jul-2016 11-01-2017
139 Setting up of 40 solar power unit at Ghataprabha in Belgaum district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka Acme Solar Holdings Private Limited Under Construction 280.00 02-Jul-2016 11-01-2017
140 Setting up of 80 MW solar power unit at Vajramatti in Bagalkot district Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka Acme Solar Holdings Private Limited Under Construction 560.00 02-Jul-2016 11-01-2017
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.