List of Infrastructure Projects – State Wise List of Infrastructure Projects – State Wise

This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9243 Total Project Cost(in Rs Crore): 6,813,036.84
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
31 20 MW Solar PV Project in Karnataka Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka Today Green Power Private Limited Under Construction 122.00 01-Nov-2014 27-09-2015
32 20 MW Solar PV Project in Karnataka - Phase II Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Karnataka Today Group Under Construction 123.00 01-Nov-2014 27-09-2015
33 20 MW Solar PV Project in Telangana Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Telangana Solairedirect Energy India Private Limited Under Construction 119.82 01-Dec-2014 27-09-2015
34 20 MW Wind Power (Jamnagar & Devbhoomi Dwarka ) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Tadas Wind Energy Private Limited Completed 100.00 Not Available 27-09-2015
35 20.1 MW Solar Power (Porbandar) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Gujarat Hiraco Renewable Energy Private Limited Completed 310.80 Not Available 27-09-2015
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.