List of Infrastructure Projects – State Wise List of Infrastructure Projects – State Wise

This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9243 Total Project Cost(in Rs Crore): 6,813,036.84
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
871 Substations (Vizianagaram) Project* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Under Construction 63.47 19-Mar-2016 25-11-2019
872 Transmission Line (Jammalamadugu-Uravakonda) Project* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Under Construction 167.67 23-Jan-2014 25-11-2019
873 Transmission Line (Maradam) Project* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Under Construction 226.63 25-Aug-2014 25-11-2019
874 Transmission Line (Narnoor-Ghani) Project* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Under Construction 82.76 03-Aug-2015 25-11-2019
875 Transmission Line (Podili-Kandukur) Project* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Under Construction 52.10 31-Mar-2016 25-11-2019
876 Transmission Line (Podili-Sattenapalli) Project* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Under Construction 148.83 03-Aug-2015 25-11-2019
877 Implementation of 132 kV substation at Pedawaltair* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Under Construction 77.51 26-Feb-2013 21-11-2019
878 Transmission Line (Chittoor) Project* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Under Construction 164.65 31-Mar-2014 21-11-2019
879 Transmission Line (Kalpaka)Project* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Under Construction 103.85 15-Sep-2014 21-11-2019
880 Construction of 220/132kV SS Chakrayapeta and connected transmission lines* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Under Construction 74.23 29-Jan-2014 05-11-2019
881 Transmission Line (Jammalamadugu-Narnoor) Project - Phase 1* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Under Construction 142.89 28-Dec-2014 05-11-2019
882 Transmission Line (Jammalamadugu-Narnoor) Project - Phase 2* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Under Construction 82.79 31-Aug-2013 05-11-2019
883 Transmission Line (Kamavarapukota-Chinnakorukondi) Project* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Under Construction 271.02 13-Mar-2014 05-11-2019
884 Transmission Line (Ramabadhrampuram) Project* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Under Construction 98.27 11-Aug-2014 05-11-2019
885 Transmission Line (Uravakonda) Project* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Under Construction 53.61 02-Aug-2013 05-11-2019
886 Substation (Hindupur) Project* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Pre-construction Stage 101.11 18-Jun-2016 25-10-2019
887 Substation (Kalikiri) Project* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Pre-construction Stage 80.74 12-Nov-2015 25-10-2019
888 Substation (Podili) Project Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Under Construction 84.65 28-Mar-2016 25-10-2019
889 Transmission Line (RTPP-Chittoor) Project* Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Pre-construction Stage 84.25 12-Nov-2015 25-10-2019
890 Transmission Line (Nunna?Jujjuru) Project Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Completed 59.00 29-Apr-2013 01-07-2019
891 Transmission Line (Rayalaseema) Project Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Completed 171.91 31-Mar-2014 01-07-2019
892 Transmission Line (Sattenapalli) Project Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Completed 59.05 30-Nov-2012 01-07-2019
893 Transmission Line (Kamavarapukota) Project Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Under Construction 64.81 13-Mar-2014 22-06-2019
894 Transmission Line (Rajapuram-Kamavarapukota) Project Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Completed 152.44 19-Feb-2014 18-08-2016
895 Transmission Line (Yemmiganur-Uravakonda) Project Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Completed 125.84 16-Dec-2013 18-08-2016
896 Transmission Line (Kamavarapukota-Vemagiri) Project Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Under Construction 170.20 25-Nov-2015 18-07-2016
897 Transmission Line (Rajapuram) Project Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Completed 97.82 21-Jul-2014 05-01-2016
898 Transmission Line (Muddanur-Chinakampally) Project Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Under Construction 65.95 16-Apr-2014 27-09-2015
899 Transmission Line (Vemagiri-Peddapuram) Project Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission Andhra Pradesh Transmission Corporation of Andhra Pradesh Limited Completed 73.07 09-Mar-2011 27-09-2015
900 Water Supply Scheme (Nanjangud) * Government Infrastructure Projects (PPP) Water Sanitation Water supply pipeline Karnataka Town Municipal Council, Nanjangud Under Construction 28.55 26-Feb-2014 04-12-2019
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.