List of Infrastructure Projects – State Wise
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
- Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
- Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
- Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
No. of Projects in this Report: | 9243 | Total Project Cost(in Rs Crore): | 6,813,036.84 |
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
61 | Ramganjmandi-Bhopal SL Railway Line | Government Infrastructure Projects (Traditional Procurement) | Transport | Railway track, tunnel, viaducts, bridges | Multi State/ Centre | West Central Railway | Under Construction | 2,909.00 | Not Available | 25-10-2019 |
62 | Shakurbasti-Rohtak Railway Line Electrification Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Railway track, tunnel, viaducts, bridges | Haryana | West Central Railway | Completed | 85.00 | Not Available | 25-10-2019 |
63 | Tiruchirapalli-Madurai Railway Line Electrification Project* | Government Infrastructure Projects (Traditional Procurement) | Transport | Railway track, tunnel, viaducts, bridges | Tamil Nadu | West Central Railway | Under Construction | 73.04 | Not Available | 25-10-2019 |
64 | Utratia-Sultanpur-Mughhalsarai Railway Line Electrification Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Railway track, tunnel, viaducts, bridges | Uttar Pradesh | West Central Railway | Completed | 137.43 | Not Available | 25-10-2019 |
65 | Lalitpur-Khajuraho-Satna-Rewa-Singrauli SL Railway Line | Government Infrastructure Projects (Traditional Procurement) | Transport | Railway track, tunnel, viaducts, bridges | Multi State/ Centre | West Central Railway | Completed | 1,631.00 | Not Available | 30-07-2019 |
66 | Khurja-Hapur-Meerut City-Saharanpur Railway Line Electrification Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Railway track, tunnel, viaducts, bridges | Uttar Pradesh | West Central Railway | Completed | 275.00 | Not Available | 18-07-2019 |
67 | Barauni-Katihar-Guwahati Railway Line Electrification Project | Government Infrastructure Projects (Traditional Procurement) | Transport | Railway track, tunnel, viaducts, bridges | Assam | West Central Railway | Under Construction | 817.12 | Not Available | 27-09-2015 |
68 | Development of 400 kV substation at New Chanditala in Hooghly district | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Transmission Company Limited | Under Construction | 154.40 | 10-Feb-2014 | 04-12-2019 |
69 | Implementation of PPSP New 400 kV GIS substation in Purulia | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Transmission Company Limited | Completed | 113.93 | 29-Sep-2015 | 04-12-2019 |
70 | Laying of 400 kV DC line between Sagardighi TPS-Gokarna | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Transmission Company Limited | Completed | 138.36 | 15-Jul-2013 | 04-12-2019 |
71 | Substation (Sadaipur) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Transmission Company Limited | Completed | 60.87 | 29-Oct-2014 | 04-12-2019 |
72 | Development of Gokarna substation of 400 kV in Murshidabad district.* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Transmission Company Limited | Under Construction | 83.07 | 20-Mar-2014 | 27-11-2019 |
73 | Laying of 139.6 CKM D/C & M/C overhead Kharagpur-Chanditala transmission line* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Transmission Company Limited | Under Construction | 243.22 | 10-Feb-2014 | 27-11-2019 |
74 | Laying of 170 CKM D/C & M/C overhead Gokarna-Chanditala transmission line* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Transmission Company Limited | Under Construction | 299.76 | 27-Sep-2014 | 27-11-2019 |
75 | Setting up of 220 kV GIS substation at Sagardighi in Murshidabad district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Transmission Company Limited | Under Construction | 56.68 | 07-Jun-2016 | 25-11-2019 |
76 | Setting up of 220 kV gas insulated substation at Gazol* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Transmission Company Limited | Under Construction | 93.17 | 30-Dec-2016 | 22-11-2019 |
77 | Setting up of 220 kV substation at Rejinagar* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Transmission Company Limited | Under Construction | 97.01 | 23-Dec-2016 | 22-11-2019 |
78 | Setting up of 220/132 kV substation at Barasat in North 24 Parganas district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Transmission Company Limited | Under Construction | 70.81 | 30-Aug-2016 | 22-11-2019 |
79 | Setting up of 220/132/33 kV substation at New Town II C in North 24 Parganas district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Transmission Company Limited | Under Construction | 98.92 | 14-Sep-2016 | 22-11-2019 |
80 | Power Transmission (Alipurduar) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Transmission Company Limited | Under Construction | 67.00 | 18-May-2015 | 02-07-2019 |
81 | Transmission Line (Kolaghat) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Transmission Company Limited | Completed | 62.29 | 30-Jun-2009 | 02-07-2019 |
82 | Laying of 220 kV Kharagpur-Vidyasagar Park D/C transmission line in Kolkata | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Transmission Company Limited | Completed | 59.71 | 28-Oct-2014 | 13-03-2017 |
83 | Setting up of 220/132 kV gas insulated substation at Vidyasagar lndustrial Park in Midnapore district | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Transmission Company Limited | Completed | 70.42 | 22-Apr-2013 | 26-12-2016 |
84 | Transmission Line (Kharagpur-Egra) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Transmission Company Limited | Completed | 68.38 | 28-Oct-2014 | 05-09-2016 |
85 | Transmission Line (Krishnanagar-Gokarna) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Transmission Company Limited | Completed | 84.72 | 07-Dec-2012 | 05-09-2016 |
86 | Substation (Kharagpur) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Transmission Company Limited | Completed | 97.34 | 11-Nov-2009 | 06-10-2015 |
87 | Transmission Line (New Town-Salt Lake) Project | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Transmission Company Limited | Completed | 52.50 | 24-Mar-2010 | 06-10-2015 |
88 | Implementation of rural electrification at Jalpaiguri, Uttar Dinajpur, Dhakshin Dinajpur etc in West Bengal under BRGF | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | West Bengal | West Bengal State Electricity Distribution Company Limited | Completed | 2,511.01 | 16-Mar-2012 | 04-12-2019 |
89 | Setting up a 10 MWp solar photovoltaic based power unit at Chharrah in Purulia district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | West Bengal | West Bengal State Electricity Distribution Company Limited | Under Construction | 60.75 | 16-Aug-2016 | 03-12-2019 |
90 | Setting up a 10 MWp solar photovoltaic based power unit at Mejia in Bankura district* | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | West Bengal | West Bengal State Electricity Distribution Company Limited | Under Construction | 60.85 | 16-Aug-2016 | 03-12-2019 |