List of Infrastructure Projects – State Wise List of Infrastructure Projects – State Wise

This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9242 Total Project Cost(in Rs Crore): 6,813,008.32
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
501 Coal Based Power (Okkur) Project Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Tamil Nadu Nagai Power Private Limited Under Construction 1,440.00 22-Sep-2010 06-06-2019
502 Coal Based Power (Sathankulam) Project Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Tamil Nadu Ind-Barath Energy Utkal Limited Under Construction 4,000.00 Not Available 06-06-2019
503 Combined Cycle Power (West Godavari) Project Phase I Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Andhra Pradesh Panduranga Energy Systems Private Limited Completed 858.00 18-Dec-2010 06-06-2019
504 Setting up of 12 MW coal based power unit at Barahamusa in Sundargarh district Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Odisha Surendra Mining Industries Private Limited Completed 72.00 21-Dec-2011 06-06-2019
505 Sinnar Coal Based Power Project Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) Maharashtra Rattan India Nasik Power Limited Completed 6,048.00 10-Jun-2010 06-06-2019
506 225 MW combined cylce gas turbine power project in Uttarakhand Government Infrastructure Projects (PPP) Energy Electricity generation (grid) Uttarakhand Operation and Maintenance Stage 1,380.00 Not Available 17-12-2018
507 Raigarh coal based thermal power project. Government Infrastructure Projects (PPP) Energy Electricity generation (grid) Chhattisgarh Operation and Maintenance Stage 9,415.00 Not Available 29-11-2018
508 Raj West Power Limited - Barmer Power Plant Government Infrastructure Projects (PPP) Energy Electricity generation (grid) Rajasthan Operation and Maintenance Stage 4,620.00 Not Available 29-11-2018
509 Samalpatti Power Project Government Infrastructure Projects (PPP) Energy Electricity generation (grid) Tamil Nadu Tamil Nadu Electricity Regulation Commission Operation and Maintenance Stage 419.05 Not Available 29-11-2018
510 Thoothukudi coal-based thermal power project phase-II Government Infrastructure Projects (PPP) Energy Electricity generation (grid) Tamil Nadu Operation and Maintenance Stage 3,514.00 Not Available 29-11-2018
511 Jas Infrastructure and Power Limited Government Infrastructure Projects (PPP) Energy Electricity generation (grid) Bihar Operation and Maintenance Stage 7,413.00 Not Available 22-11-2018
512 MEIL Green Power (Anantpur) Limited 50MW CSP Government Infrastructure Projects (PPP) Energy Electricity generation (grid) Andhra Pradesh Operation and Maintenance Stage 848.00 Not Available 22-11-2018
513 VISA Raigarh Power Project Phase I Government Infrastructure Projects (PPP) Energy Electricity generation (grid) Chhattisgarh Operation and Maintenance Stage 3,930.00 Not Available 22-11-2018
514 189 MW Thoothukudi thermal power plant Government Infrastructure Projects (PPP) Energy Electricity generation (grid) Tamil Nadu Operation and Maintenance Stage 760.00 Not Available 20-11-2018
515 Amravati Thermal Power Project Phase-I Government Infrastructure Projects (PPP) Energy Electricity generation (grid) Maharashtra Operation and Maintenance Stage 6,515.00 Not Available 20-11-2018
516 Anpara C Thermal Power Station Government Infrastructure Projects (PPP) Energy Electricity generation (grid) Uttar Pradesh Operation and Maintenance Stage 4,845.00 Not Available 20-11-2018
517 Coal based thermal power plant at Tuticorin in tamil Nadu Government Infrastructure Projects (PPP) Energy Electricity generation (grid) Tamil Nadu Tamil Nadu Generation and Distribution Corporation Limited Operation and Maintenance Stage 1,071.00 Not Available 20-11-2018
518 East Coast Energy Private Limited (ECEPL) - Coal based Thermal Power Plant near Kakarapalli Village Government Infrastructure Projects (PPP) Energy Electricity generation (grid) Andhra Pradesh Operation and Maintenance Stage 9,343.15 Not Available 20-11-2018
519 EMCO Energy Limited - Coal based power plant located in Chandrapur Government Infrastructure Projects (PPP) Energy Electricity generation (grid) Maharashtra Operation and Maintenance Stage 4,250.00 Not Available 20-11-2018
520 Gautami Combined Cycle Power Plant Government Infrastructure Projects (PPP) Energy Electricity generation (grid) Andhra Pradesh Operation and Maintenance Stage 1,800.00 Not Available 20-11-2018
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.