List of Infrastructure Projects – State Wise List of Infrastructure Projects – State Wise

This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9243 Total Project Cost(in Rs Crore): 6,813,036.84
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
76 Wind Power (Piploda 15MW) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh NSL Renewable Power Private Limited Under Construction 105.00 14-Aug-2013 26-02-2016
77 Wind Power (Piploda 14MW) Project* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh Naveen Wind Mill, Jabalpur Under Construction 98.00 24-Jul-2013 21-11-2019
78 Wind Power (Piploda - 9MW) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh Saakar Energy Private Limited Under Construction 63.00 13-Oct-2014 28-02-2016
79 Wind Power (Petlawad - 81.9MW) Project* Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh Saimran Realities Limited Under Construction 573.30 16-Sep-2014 21-11-2019
80 Wind Power (Petlawad - 49.5MW) Project Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) Madhya Pradesh Amboli Power Private Limited Under Construction 346.50 25-Aug-2014 26-02-2016
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.