List of Infrastructure Projects – State Wise
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
- Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
- Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
- Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
No. of Projects in this Report: | 9243 | Total Project Cost(in Rs Crore): | 6,813,036.84 |
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
361 | Rural Electrification (Saran) Project [RGGVY-XII]#* | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Bihar | North Bihar Power Distribution Company Limited | Under Construction | 447.98 | 21-Aug-2014 | 04-12-2019 |
362 | Rural Electrification (Shajapur) Project - RGGVY 11th Plan-Phase II | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Madhya Pradesh | Madhya Pradesh Paschim Kshetra Vidyut Vitaran Company Limited | Under Construction | 55.08 | 26-Mar-2012 | 04-12-2019 |
363 | Rural Electrification (Shivpuri) - (RGGVY) Phase 1 | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Madhya Pradesh | Madhya Pradesh Madhya Kshetra Vidyut Vitaran Company Limited | Under Construction | 60.13 | 31-Dec-2009 | 04-12-2019 |
364 | Rural Electrification (Shivpuri) - (RGGVY) Phase 2 | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Madhya Pradesh | Madhya Pradesh Madhya Kshetra Vidyut Vitaran Company Limited | Under Construction | 66.07 | 25-Sep-2014 | 04-12-2019 |
365 | Rural Electrification (Siwan) Project - RGGVY 11th Plan Phase-II | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Bihar | North Bihar Power Distribution Company Limited | Under Construction | 380.90 | 19-Nov-2013 | 04-12-2019 |
366 | Rural Electrification (Vidisha) - (RGGVY) | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Madhya Pradesh | Madhya Pradesh Madhya Kshetra Vidyut Vitaran Company Limited | Under Construction | 73.99 | 29-Dec-2015 | 04-12-2019 |
367 | Sardar Sarovar Project (Narmada) | Government Infrastructure Projects (Traditional Procurement) | Water Sanitation | Irrigation (dams, channels, embankments, etc.) | Gujarat | Sardar Sarovar Narmada Nigam Limited | Under Construction | 39,240.45 | Not Available | 04-12-2019 |
368 | Satpura Thermal Power Project# | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Madhya Pradesh | Madhya Pradesh Power Generating Company Limited | Completed | 3,514.00 | 27-Feb-2009 | 04-12-2019 |
369 | Setting up 20 MW hydel based power unit at Telbeila in Pune | Government Infrastructure Projects (PPP) | Energy | Renewable energy (grid) | Maharashtra | Water Resources Department, Maharashtra | Pre-construction Stage | 115.44 | 06-Jul-2013 | 04-12-2019 |
370 | Setting up a 1,200 MW coal based power plant Phase I (Unit 1 & 2) at Raghunathpur# | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | West Bengal | Damodar Valley Corporation | Completed | 8,781.30 | 14-Dec-2007 | 04-12-2019 |
371 | Setting up a 13.6 MW wind based power unit at Lodurva | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Rajasthan | Oil India Limited | Completed | 85.60 | 10-Feb-2012 | 04-12-2019 |
372 | Setting up of 500 MW Barauni thermal power unit in Begusarai district | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Bihar | Bihar State Power Generation Company Limited | Under Construction | 5,308.07 | 11-Mar-2011 | 04-12-2019 |
373 | Setting up of 10 MW solar based power unit at Paradip Port in Jagatsinghpur district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Odisha | Paradip Port Trust | Completed | 100.00 | 28-Nov-2016 | 04-12-2019 |
374 | Setting Up of 10 MW Solar Power Unit at Visakhapatnam Port Trust * | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Andhra Pradesh | Visakhapatnam Port Trust | Under Construction | 60.00 | 02-Nov-2015 | 04-12-2019 |
375 | Setting up of 10 TPD solid waste management unit at Pernem # | Government Infrastructure Projects (PPP) | Water Sanitation | Solid waste management | Goa | State Urban Development Agency, Goa | Under Construction | 15.00 | 12-Nov-2014 | 04-12-2019 |
376 | Setting up of 100 MW Sainj hydel power unit at Kullu# | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Himachal Pradesh | Himachal Pradesh Power Corporation Limited | Completed | 676.29 | 02-Aug-2010 | 04-12-2019 |
377 | Setting up of 100 MW Solar Power unit at Bhagwanpur | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | Uttarakhand Renewable Energy Development Agency | Completed | 700.00 | 20-Sep-2016 | 04-12-2019 |
378 | Setting up of 1000 MW coal based power unit at Chandrapur district | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Maharashtra | Maharashtra State Power Generation Company Limited | Completed | 7,004.42 | 25-Jul-2008 | 04-12-2019 |
379 | Setting up of 1000 MW coal based power unit at Nabinagar# | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Bihar | Bharatiya Rail Bijlee Company Limited | Completed | 7,998.00 | 22-Jan-2008 | 04-12-2019 |
380 | Setting up of 110 MW Pare hydel power unit in Papumpare# | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Arunachal Pradesh | North Eastern Electric Power Corporation Limited | Under Construction | 1,640.00 | 01-Sep-2009 | 04-12-2019 |
381 | Setting up of 120 MW hydel power project at Pulichintala in Guntur and Nalgonda# | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Telangana | Telangana State Power Generation Corporation Limited | Completed | 563.50 | 11-Jun-2007 | 04-12-2019 |
382 | Setting up of 120 MW Rammam III hydel power unit at Darjeeling | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | West Bengal | NTPC Limited | Under Construction | 1,592.34 | 10-Sep-2014 | 04-12-2019 |
383 | Setting up of 1320 MW Suratgarh thermal power station at Suratgarh - Stage-V | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Rajasthan | Rajasthan Rajya Vidyut Utpadan Nigam Limited | Completed | 6,192.37 | 28-May-2013 | 04-12-2019 |
384 | Setting up of 171 MW Lata Tapovan hydel power unit at Chamoli# | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Uttarakhand | NTPC Limited | Completed | 1,801.07 | 07-Dec-2012 | 04-12-2019 |
385 | Setting up of 1980 MW coal based power unit at Barh in Patna | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity generation (grid) | Bihar | NTPC Limited | Under Construction | 15,095.67 | 14-Mar-2005 | 04-12-2019 |
386 | Setting up of 200 MW wind based power at Thoothukudi | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Tamil Nadu | Solar Energy Corporation of India | Completed | 1,000.00 | 16-Oct-2017 | 04-12-2019 |
387 | Setting up of 21 MW wind based power unit at Nakhatrana Wind Farm in Kachchh district | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Gujarat | Gujarat Industries Power Company Limited | Completed | 105.00 | 30-Apr-2016 | 04-12-2019 |
388 | Setting up of 220 kV substation at Anjangaon in Amravati district | Government Infrastructure Projects (Traditional Procurement) | Energy | Electricity transmission | Maharashtra | Maharashtra State Electricity Transmission Company Limited | Completed | 51.04 | 09-Feb-2010 | 04-12-2019 |
389 | Setting up of 240 MW Lower Jurala hydel power unit at Mahaboob Nagar | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Telangana | Telangana State Power Generation Corporation Limited | Completed | 1,969.14 | 14-Jul-2008 | 04-12-2019 |
390 | Setting up of 25 MW biomass based co-generation power plant at Naraingarh | Government Infrastructure Projects (Traditional Procurement) | Energy | Renewable energy (grid) | Haryana | Haryana Renewable Energy Development Agency | Completed | 116.09 | 12-Sep-2012 | 04-12-2019 |