List of Infrastructure Projects – State Wise List of Infrastructure Projects – State Wise

This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria:
  • Government Infrastructure Projects (PPP) that were either under 'Pre-construction Stage', 'Under Construction' or 'Operation and Maintenance Stage' as on April 1, 2011 or 'Awarded' thereafter and with Project Cost >INR 5 crore.
  • Government Infrastructure Projects (Traditional Procurement) that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore; and
  • Private Sector Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 06 December 2019
No. of Projects in this Report: 9242 Total Project Cost(in Rs Crore): 6,813,008.32
State selection
Please Select State:
This Report provides State/UT wise information on infrastructure projects across pre-defined set of parameters and following coverage criteria: (All States)
Sl No
1 Bus Rapid Transit System (Ultadanga-Garia) Government Infrastructure Projects (Traditional Procurement) Transport Urban public transport (except rolling stock) West Bengal Kolkata Metropolitan Development Authority Under Construction 252.91 16-Jun-2010 04-12-2019
2 Construction of EM-Bypass connector from Padmapukur to Kamalgazi in Kolkata district Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges West Bengal Kolkata Metropolitan Development Authority Completed 77.72 28-Dec-2007 04-12-2019
3 Construction of pedestrian skywalk at Dakshineswar temple area in Kolkata district Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges West Bengal Kolkata Metropolitan Development Authority Completed 65.00 16-Mar-2015 04-12-2019
4 Development of 400 kV substation at New Chanditala in Hooghly district Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission West Bengal West Bengal State Electricity Transmission Company Limited Under Construction 154.40 10-Feb-2014 04-12-2019
5 East West Metro Corridor Project Government Infrastructure Projects (Traditional Procurement) Transport Urban public transport (except rolling stock) West Bengal Kolkata Metro Rail Corporation Limited Under Construction 4,874.58 30-Jul-2008 04-12-2019
6 Eco Tourism (Sabujdweep Island) Project Government Infrastructure Projects (PPP) Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ West Bengal Department of Tourism, West Bengal Under Construction 54.00 14-Aug-2015 04-12-2019
7 Expansion of Kolkata metro rail in length of 81.0 Km - Phase II Government Infrastructure Projects (Traditional Procurement) Transport Urban public transport (except rolling stock) West Bengal Rail Vikas Nigam Limited Under Construction 11,000.00 21-Oct-2011 04-12-2019
8 Flyover (Parama-Park Circus) Project Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges West Bengal Kolkata Metropolitan Development Authority Completed 291.66 22-Jan-2009 04-12-2019
9 Four laning of Islampur bypass in length of 10.3 km in North Dinajpur under NHDP-II Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges West Bengal National Highways Authority of India (NHAI) Under Construction 361.15 15-Jan-2016 04-12-2019
10 Four laning of Silchar-Agartala section in length of 306.0 km Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges West Bengal National Highways and Infrastructure Development Corporation Limited Completed 3,060.00 18-Oct-2016 04-12-2019
11 Implementation of 1000 MW coal based power unit at Sagardighi Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) West Bengal West Bengal Power Development Corporation Limited Completed 5,340.00 22-Feb-2011 04-12-2019
12 Implementation of 13.1 MLD water supply scheme at Simlapal in Bankura Government Infrastructure Projects (Traditional Procurement) Water Sanitation Water supply pipeline West Bengal Public Health Engineering Department, West Bengal Completed 51.21 22-Jan-2013 04-12-2019
13 Implementation of 147 MLD piped water supply scheme at Habra-Gaighata* Government Infrastructure Projects (Traditional Procurement) Water Sanitation Water supply pipeline West Bengal Public Health Engineering Department, West Bengal Under Construction 577.72 22-Mar-2015 04-12-2019
14 Implementation of 15.3 MLD water supply scheme at Bishnupur Government Infrastructure Projects (Traditional Procurement) Water Sanitation Water supply pipeline West Bengal Public Health Engineering Department, West Bengal Completed 64.17 14-May-2013 04-12-2019
15 Implementation of 16.8 MLD piped water supply scheme at Beldanga-I in Murshidabad* Government Infrastructure Projects (Traditional Procurement) Water Sanitation Water supply pipeline West Bengal Public Health Engineering Department, West Bengal Under Construction 54.21 09-Dec-2013 04-12-2019
16 Implementation of 19.3 MLD water supply scheme at Indus in Bankura Government Infrastructure Projects (Traditional Procurement) Water Sanitation Water supply pipeline West Bengal Public Health Engineering Department, West Bengal Completed 68.36 19-Dec-2012 04-12-2019
17 Implementation of PPSP New 400 kV GIS substation in Purulia Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission West Bengal West Bengal State Electricity Transmission Company Limited Completed 113.93 29-Sep-2015 04-12-2019
18 Implementation of rural electrification at Jalpaiguri, Uttar Dinajpur, Dhakshin Dinajpur etc in West Bengal under BRGF Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission West Bengal West Bengal State Electricity Distribution Company Limited Completed 2,511.01 16-Mar-2012 04-12-2019
19 Laying of New Coochbehar-Gumanihat DL railway line in length of 29.3 km Government Infrastructure Projects (Traditional Procurement) Transport Railway track, tunnel, viaducts, bridges West Bengal Northeast Frontier Railway Completed 451.00 01-Apr-2015 04-12-2019
20 Laying of 400 kV DC line between Sagardighi TPS-Gokarna Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission West Bengal West Bengal State Electricity Transmission Company Limited Completed 138.36 15-Jul-2013 04-12-2019
21 Laying of Ambari Falakata-New Moynaguri DL railway line in length of 36.5 km Government Infrastructure Projects (Traditional Procurement) Transport Railway track, tunnel, viaducts, bridges West Bengal Northeast Frontier Railway Under Construction 551.00 07-Oct-2015 04-12-2019
22 Laying of Kaliyaganj-Buniadpur railway line in length of 33.13 km Government Infrastructure Projects (Traditional Procurement) Transport Railway track, tunnel, viaducts, bridges West Bengal Northeast Frontier Railway Under Construction 380.00 30-Apr-2010 04-12-2019
23 Road Upgradation (Gammon Bridge-Gandhi More) Project Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges West Bengal Asansol Durgapur Development Authority Completed 77.82 02-Aug-2012 04-12-2019
24 Setting up a 1,200 MW coal based power plant Phase I (Unit 1 & 2) at Raghunathpur# Government Infrastructure Projects (Traditional Procurement) Energy Electricity generation (grid) West Bengal Damodar Valley Corporation Completed 8,781.30 14-Dec-2007 04-12-2019
25 Setting up of 120 MW Rammam III hydel power unit at Darjeeling Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) West Bengal NTPC Limited Under Construction 1,592.34 10-Sep-2014 04-12-2019
26 Substation (Sadaipur) Project Government Infrastructure Projects (Traditional Procurement) Energy Electricity transmission West Bengal West Bengal State Electricity Transmission Company Limited Completed 60.87 29-Oct-2014 04-12-2019
27 Teesta Low Dam-III (4X33=132MW) Government Infrastructure Projects (Traditional Procurement) Energy Renewable energy (grid) West Bengal NHPC Limited Completed 1,972.99 31-Oct-2003 04-12-2019
28 Two laning of existing carriageway between Moledanga-Bashbandh in length of 27.4 KM Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges West Bengal Public Works Department, West Bengal Completed 135.94 06-May-2015 04-12-2019
29 Two laning of Falakata-Pundibari section in length of 26.0 Km Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges West Bengal Public Works Department, West Bengal Completed 64.27 18-Mar-2013 04-12-2019
30 Upgradation of Airport Gate-Duckbunglow More Road in length of 7.2 Km Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges West Bengal Public Works Department, West Bengal Completed 80.90 10-Nov-2014 04-12-2019
31 Upgradation of carriageway in length of 37 km in Birbhum Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges West Bengal Public Works Department, West Bengal Completed 97.38 22-Nov-2011 04-12-2019
32 Upgradation of Kochigaon-Birpara road in length of 123.0 km Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges West Bengal National Highways and Infrastructure Development Corporation Limited Completed 1,230.00 18-Oct-2016 04-12-2019
33 Water Drainage System (Digha) Government Infrastructure Projects (Traditional Procurement) Water Sanitation Storm water drainage system West Bengal Digha Sankarpur Development Authority Under Construction 63.98 01-Jan-2013 04-12-2019
34 Water Supply (Kandi) Project * Government Infrastructure Projects (Traditional Procurement) Water Sanitation Water supply pipeline West Bengal Department of Municipal Affairs, West Bengal Under Construction 56.85 30-Jun-2009 04-12-2019
35 Water Supply Scheme (Bankura-I, Bankura-II & Barjora) BRGF - Phase I Government Infrastructure Projects (Traditional Procurement) Water Sanitation Water supply pipeline West Bengal Public Health Engineering Department, West Bengal Completed 289.10 11-Oct-2012 04-12-2019
36 Water Supply Scheme (Onda) BRGF - Phase I Government Infrastructure Projects (Traditional Procurement) Water Sanitation Water supply pipeline West Bengal Public Health Engineering Department, West Bengal Completed 179.47 13-Nov-2012 04-12-2019
37 Water Supply Scheme (Saltora-Chhatna) BRGF - Phase I Government Infrastructure Projects (Traditional Procurement) Water Sanitation Water supply pipeline West Bengal Public Health Engineering Department, West Bengal Completed 159.31 23-Nov-2012 04-12-2019
38 Bridge (Gokulpur-Midnapur) Project * Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges West Bengal South Eastern Railway Under Construction 52.00 Not Available 03-12-2019
39 Bridge (Nakatti) Project Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges West Bengal Public Works Department, West Bengal Completed 289.69 21-Sep-2015 03-12-2019
40 Construction of bridge over Katakhali river of 2.8 km at Hasnabad in North 24 Parganas* Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges West Bengal Public Works Department, West Bengal Under Construction 81.30 01-Jun-2015 03-12-2019
41 Construction of high level major bridge on Hatania-Doania river in South 24 Parganas district Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges West Bengal Public Works Department, West Bengal Completed 225.93 19-Dec-2014 03-12-2019
42 Construction of sewerage network in length of 11.7 km at Thakurpara in Murshidabad district* Government Infrastructure Projects (Traditional Procurement) Water Sanitation Sewage collection, treatment and disposal system West Bengal Kolkata Municipal Corporation Under Construction 82.41 16-Nov-2016 03-12-2019
43 Construction of sewerage network in length of 14.5 km at Mahatma Gandhi road in Kolkata district* Government Infrastructure Projects (Traditional Procurement) Water Sanitation Sewage collection, treatment and disposal system West Bengal Kolkata Municipal Corporation Under Construction 69.48 17-Oct-2016 03-12-2019
44 Construction of sewerage network in length of 3.8 km along James Long Sarani in Kolkata district* Government Infrastructure Projects (Traditional Procurement) Water Sanitation Sewage collection, treatment and disposal system West Bengal Kolkata Municipal Corporation Under Construction 98.71 17-Oct-2016 03-12-2019
45 Construction of water pipeline in length of 153 km at Cossipore Service zone, Ward No.1 to 6 in Kolkata Government Infrastructure Projects (Traditional Procurement) Water Sanitation Water supply pipeline West Bengal Kolkata Municipal Corporation Completed 212.40 04-Oct-2016 03-12-2019
46 Drainage Scheme (Howrah)* Government Infrastructure Projects (Traditional Procurement) Water Sanitation Storm water drainage system West Bengal Kolkata Metropolitan Development Authority Under Construction 93.38 08-Jan-2007 03-12-2019
47 LPG Storage Plant (Panagarh)* Government Infrastructure Projects (Traditional Procurement) Energy Oil/ Gas/ LNG Storage West Bengal Hindustan Petroleum Corporation Limited Under Construction 190.00 17-Sep-2014 03-12-2019
48 Refurbishment of 20 MGD water supply scheme at Palta & Garden Reach in Kolkata Government Infrastructure Projects (Traditional Procurement) Water Sanitation Water supply pipeline West Bengal Kolkata Municipal Corporation Completed 80.56 07-Nov-2014 03-12-2019
49 Road Upgradation (Arambagh-Goghat-Ramjibanpur) Project Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges West Bengal Public Works Department, West Bengal Completed 96.67 07-Jul-2014 03-12-2019
50 Road Upgradation (Changrabandha-Mathabhanga-Coochbehar) Project Government Infrastructure Projects (Traditional Procurement) Transport Roads and bridges West Bengal Public Works Department, West Bengal Completed 175.27 20-Jan-2015 03-12-2019
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis. Contact project sponsoring authorities to seek additional details.

# - The project may have additional details that are pertinent. Kindly check the 'Any Other Information' field for further details.
* - Updated status for the project is not available.