List of Infrastructure Project List of Infrastructure Project

This Report provides information on infrastructure projects implemented by the Government through traditional procurement (i.e. EPC basis) across pre-defined set of parameters and following coverage criteria:
  • Projects that were under 'Pre-construction Stage', or 'Under Construction' as on April 1, 2012 or 'Awarded' thereafter and with Project Cost >INR 50 crore.
Information available as on 22 August 2019
Please click on project name for more details of the project.
Search
This search option only displays the results based on project name and project brief. For detailed search based on other project parameters, please click on the link provided below.
Design Your Search
No. of Projects in this Report: 6249 Total Project Cost(in Rs Crore): 3,416,791.70
Sl No
121 Implementation of rural electrification works in Rajkot under DDUGJY scheme
66.00 KV (Kilo Volt) 58.68 Energy Electricity transmission Completed Paschim Gujarat Vij Company Limited 14-Aug-2015 Gujarat 16-08-2019
122 Implementation of rural electrification works in Rajkot under Integrated Power Development Scheme
33.00 KV (Kilo Volt) 126.53 Energy Electricity transmission Completed Paschim Gujarat Vij Company Limited 19-Oct-2015 Gujarat 16-08-2019
123 Implementation of rural electrification works in Sawai Madhopur under RGGVY-12th Plan
11.00 KV (Kilo Volt) 52.02 Energy Electricity transmission Completed Jaipur Electricity Distribution Corporation Limited 02-Jun-2015 Rajasthan 16-08-2019
124 Implementation of rural electrification works in Surat under Integrated Power Development Scheme
33.00 KV (Kilo Volt) 94.91 Energy Electricity transmission Completed Dakshin Gujarat Vij Company Limited 21-Mar-2016 Gujarat 16-08-2019
125 Implementation of rural electrification works in Tapi & Valsad under DDUGJY scheme
66.00 KV (Kilo Volt) 56.49 Energy Electricity transmission Completed Dakshin Gujarat Vij Company Limited 14-Aug-2015 Gujarat 16-08-2019
126 Implementation of rural electrification works in Tonk under DDUGJY
33.00 KV (Kilo Volt) 60.01 Energy Electricity transmission Completed Jaipur Electricity Distribution Corporation Limited 27-Jan-2017 Rajasthan 16-08-2019
127 Implementation of rural electrification works in Udham Singh Nagar under DDUGJY
33.00 KV (Kilo Volt) 149.12 Energy Electricity transmission Completed Uttarakhand Power Corporation Limited 11-Aug-2017 Uttarakhand 16-08-2019
128 Implementation of rural electrification works in Vadodara under DDUGJY scheme
66.00 KV (Kilo Volt) 70.40 Energy Electricity transmission Completed Madhya Gujarat Vij Company Limited 14-Aug-2015 Gujarat 16-08-2019
129 Implementation of rural electrification works in Valsad & Bharuch under Integrated Power Development Scheme
33.00 KV (Kilo Volt) 59.40 Energy Electricity transmission Completed Dakshin Gujarat Vij Company Limited 21-Mar-2016 Gujarat 16-08-2019
130 Inkel Business Park
5.50 Acres 75.00 Social and Commercial Infrastructure Common infrastructure for industrial parks, SEZ Completed INKEL Limited 01-Apr-2010 Kerala 16-08-2019
131 Integrated Power Development Scheme (Bareilly)
33.00 KV (Kilo Volt) 69.70 Energy Electricity transmission Completed Madhyanchal Vidyut Vitaran Nigam Limited 31-Aug-2016 Uttar Pradesh 16-08-2019
132 Irrigation (Hirepadasalagi) Project
8,648.70 Acres 100.74 Water Sanitation Irrigation (dams, channels, embankments, etc.) Completed Krishna Bhagya Jala Nigam Limited 09-Jan-2009 Karnataka 16-08-2019
133 Kalyan-Kasara Third Railway Line Project
68.00 KM (Kilometer) 792.89 Transport Railway track, tunnel, viaducts, bridges Under Construction Not Available Maharashtra 16-08-2019
134 Khodri-Anuppur GC Railway Line Project
61.60 KM (Kilometer) 386.00 Transport Railway track, tunnel, viaducts, bridges Completed South East Central Railway Not Available Chhattisgarh 16-08-2019
135 Khurda-Barang Third Railway Line
35.00 KM (Kilometer) 385.00 Transport Railway track, tunnel, viaducts, bridges Under Construction Rail Vikas Nigam Limited 08-Aug-2006 Odisha 16-08-2019
136 Laying of 320 kV Raigarh-Pugalur-Madakathara transmission line - Scheme 3
320.00 KV (Kilo Volt) 3,769.00 Energy Electricity transmission Completed Power Grid Corporation of India Limited 22-Mar-2017 Multi State/ Centre 16-08-2019
137 Laying of 400 KV Pugalur-Edayarpalayam & Edayarpalayam-Udumalpet D/C line
400.00 KV (Kilo Volt) 107.56 Energy Electricity transmission Completed Power Grid Corporation of India Limited 27-Sep-2017 Multi State/ Centre 16-08-2019
138 Laying of 45 km third railway line between Panskura and Kharagpur
45.00 KM (Kilometer) 405.62 Transport Railway track, tunnel, viaducts, bridges Completed Rail Vikas Nigam Limited 21-May-2009 West Bengal 16-08-2019
139 Laying of 81 km third line for Palwal-Bhuteshwar district
81.00 KM (Kilometer) 413.46 Transport Railway track, tunnel, viaducts, bridges Completed Rail Vikas Nigam Limited 08-May-2006 Multi State/ Centre 16-08-2019
140 Manglia-Piyala Product Pipeline Project
800.00 KM (Kilometer) 807.46 Energy Oil pipelines Completed Bharat Petroleum Corporation Limited 30-Sep-2004 Multi State/ Centre 16-08-2019
Note: Zero indicates information not available.

These reports are based on data received from relevant Project Authorities and is being updated on a best endeavor basis.